6113 1/2 S WEST BLVD 90043

Certificate Information: 6113 1/2 S WEST BLVD 90043

Application / Permit
24016-10000-29894
Plan Check / Job No.
B24LA23362
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Eplan. Convert (E) Garage at 1st floor within (E) 3 story Duplex/ Garage to Attached ADU/DUPLEX. Sprinklered NFPA13R.
Permit Issued
Issued on 10/18/2024
Issuing Office
Current Status
CofO Issued on 7/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/19/2024 APPLICANT
Assigned to Plan Check Engineer 9/23/2024 SAMUEL GONZALEZ
Corrections Issued 9/24/2024 SAMUEL GONZALEZ
Applicant returned to address corrections 10/9/2024 ADAM HEGAZI
Plan Check Approved 10/17/2024 TSE MING HUANG
Issued 10/18/2024 APPLICANT
CofO in Progress 7/11/2025 MICHAEL LEWIS
Permit Finaled 7/16/2025 DEROLD HAUFF
CofO Issued 7/16/2025 DEROLD HAUFF
Permit Finaled 7/16/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/11/2024 CHRISTINA BRACO
Sewer availability Cleared 10/11/2024 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 10/15/2024 ABEL CASILLAS

Contact Information

Architect Kelly,, Jonathan Stanleigh; Lic. No.: C34283 4819 TEMPLETON STREET      LOS ANGELES, CA 90032
Contractor Aardvark Group Inc The; Lic. No.: 762498-B       ,
Contractor The Aardvark Group Inc; Lic. No.: 762498-B       ,
Engineer Judd,, Steven George; Lic. No.: C72583 6362 W MT SHASTA CT      WEST VALLEY CITY, UT 84118

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/22/2024 Corrections Issued AMIR NAZARIAN
Footing/Foundation/Slab 10/28/2024 Corrections Issued AMIR NAZARIAN
Underground Mechanical 10/28/2024 Partial Approval AMIR NAZARIAN
Footing/Foundation/Slab 10/30/2024 Conditional Approval AMIR NAZARIAN
PLUMBING-Rough 11/15/2024 Corrections Issued AMIR NAZARIAN
BUILDING-Rough-Frame 11/19/2024 Not Ready for Inspection AMIR NAZARIAN
ELECTRICAL-Rough 11/19/2024 Not Ready for Inspection AMIR NAZARIAN
HVAC-Rough 11/19/2024 Not Ready for Inspection AMIR NAZARIAN
ELECTRICAL-Rough 11/21/2024 Corrections Issued AMIR NAZARIAN
ELECTRICAL-Rough 12/3/2024 Approved AMIR NAZARIAN
BUILDING-Rough-Frame 12/5/2024 Not Ready for Inspection LUIS CASTRO
HVAC-Rough 12/10/2024 Approved LUIS CASTRO
PLUMBING-Rough 12/10/2024 Approved LUIS CASTRO
BUILDING-Rough-Frame 12/12/2024 Corrections Issued AMIR NAZARIAN
BUILDING-Rough-Frame 12/17/2024 Approved NICHOLAS LOPEZ
Insulation 12/23/2024 Corrections Issued AMIR NAZARIAN
Interior/Exterior Lathing 12/23/2024 Partial Approval AMIR NAZARIAN
Insulation 12/27/2024 Approved ANTHONY RAMOS
Drywall Nailing 1/6/2025 Approved NICHOLAS LOPEZ
PLUMBING-Final 5/15/2025 Corrections Issued WAYNE REGESTER
HVAC-Final 5/22/2025 Corrections Issued WAYNE REGESTER
ELECTRICAL-Final 6/2/2025 Corrections Issued WAYNE REGESTER
HVAC-Final 6/2/2025 Not Ready for Inspection WAYNE REGESTER
PLUMBING-Final 6/2/2025 Not Ready for Inspection WAYNE REGESTER
Final 6/3/2025 Not Ready for Inspection WAYNE REGESTER
Green Building Final 6/3/2025 Approved WAYNE REGESTER
Pre-Inspection 6/3/2025 Approved WAYNE REGESTER
SGSOV-Seismic Gas S/O Valve 6/3/2025 SGSOV Not Required WAYNE REGESTER
Service/Power Release 6/3/2025 Approved WAYNE REGESTER
Smoke Detectors 6/3/2025 Not Ready for Inspection WAYNE REGESTER
Final 6/25/2025 Not Ready for Inspection WAYNE REGESTER
Smoke Detectors 6/25/2025 Partial Approval WAYNE REGESTER
Final 7/11/2025 OK to Issue CofO MICHAEL LEWIS
Smoke Detectors 7/11/2025 Approved MICHAEL LEWIS