2506 W SCOTT AVE 90026
Certificate Information: 2506 W SCOTT AVE 90026
- Application / Permit
- 24016-10000-29736
- Plan Check / Job No.
- B24LA23137
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE INTO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). (N) UNCOVERED DECK ATTACHED TO ADU. WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 12/4/2024
- Issuing Office
- Current Status
- CofO Issued on 12/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/20/2024 | ALEC MOUSAKHANIAN |
| Corrections Issued | 9/21/2024 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 10/9/2024 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 10/15/2024 | MADISON O'DELL |
| Issued | 12/4/2024 | APPLICANT |
| CofO in Progress | 12/17/2025 | HAMIK HARTOUNIAN |
| Permit Finaled | 12/18/2025 | DEROLD HAUFF |
| CofO Issued | 12/18/2025 | DEROLD HAUFF |
| Permit Finaled | 12/18/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/5/2024 | ABEL CASILLAS |
| Roof/Waste drainage to street | Cleared | 10/5/2024 | ABEL CASILLAS |
| Sewer availability | Cleared | 10/5/2024 | ABEL CASILLAS |
| Grading Pre-Inspection | Cleared | 10/7/2024 | MICHAEL TEMPLE |
| Eng Process Fee Ord 176,300 | Cleared | 10/11/2024 | ABEL CASILLAS |
Contact Information
| Contractor | Smart Eye Construction Corp; Lic. No.: 1077004-B | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 12/19/2024 | Not Ready for Inspection | WILLIAM SIERRA |
| Underground Mechanical | 12/19/2024 | Partial Approval | WILLIAM SIERRA |
| Excavation/Setback/Form/Re-Bar | 12/31/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 1/10/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 1/15/2025 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2025 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 2/14/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2025 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 4/8/2025 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 4/8/2025 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 4/29/2025 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Rough | 4/29/2025 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 5/1/2025 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 5/1/2025 | Approved | FREDDIE RIVERA |
| Insulation | 5/8/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 5/20/2025 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 5/20/2025 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 5/20/2025 | Approved | HAMIK HARTOUNIAN |
| Underground Mechanical | 8/29/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 9/25/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 9/25/2025 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 9/25/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 10/10/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 10/10/2025 | SGSOV No Gas | HAMIK HARTOUNIAN |
| Smoke Detectors | 10/10/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 12/5/2025 | Partial Inspection | HAMIK HARTOUNIAN |
| Final | 12/16/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Service/Power Release | 12/16/2025 | Approved | HAMIK HARTOUNIAN |