555 S FLOWER ST SUITE 1300 90071

Certificate Information: 555 S FLOWER ST SUITE 1300 90071

Application / Permit
24016-10000-29551
Plan Check / Job No.
B24LA22903
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
SUITE 1300- PARTIAL FLOOR NON-STRUCTURAL INTERIOR OFFICE TI. WORK INCLUDING NON STRUCTURAL INTERIOR DEMO, NEW NON-BEARING PARTITIONS, CEILING, MILLWORK, FINISHES. SEE COMMENT
Permit Issued
Issued on 12/13/2024
Issuing Office
Current Status
Permit Finaled on 6/25/2025

Permit Application Status History

Submitted 9/16/2024 APPLICANT
Assigned to Plan Check Engineer 9/20/2024 MINA HABILI
Corrections Issued 9/21/2024 MINA HABILI
Building Plans Picked Up 10/1/2024 APPLICANT
Plan Check Approved 12/9/2024 NGHI SU
Issued 12/13/2024 APPLICANT
Permit Finaled 6/23/2025 PAUL BAZERKANIAN

Permit Application Clearance Information

Fire Marshal Fire Life Safety Cleared 12/5/2024 VIDAL GARCIA

Contact Information

Architect Lunn,, Matthew; Lic. No.: C37911    43 VISTA CIRCLE DRIVE    SIERRA MADRE, CA 91024
Contractor Howard Building Corporation; Lic. No.: 445804-B 707 WILSHIRE BLVD STE 3750      LOS ANGELES, CA 90017

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/4/2025 Partial Inspection PAUL BAZERKANIAN
Light Gage Steel Frame 2/19/2025 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 2/25/2025 Partial Approval PAUL BAZERKANIAN
Insulation 2/25/2025 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 2/28/2025 Partial Approval PAUL BAZERKANIAN
Light Gage Steel Frame 2/28/2025 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 3/7/2025 Partial Approval PAUL BAZERKANIAN
Insulation 3/7/2025 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 3/11/2025 Partial Approval PAUL BAZERKANIAN
Pre-Inspection 3/20/2025 Not Ready for Inspection PAUL BAZERKANIAN
Light Gage Steel Frame 4/3/2025 Not Ready for Inspection PAUL BAZERKANIAN
T-Bar Ceiling 4/11/2025 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 4/14/2025 Partial Approval PAUL BAZERKANIAN
Light Gage Steel Frame 4/14/2025 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 4/17/2025 Partial Approval PAUL BAZERKANIAN
Light Gage Steel Frame 4/18/2025 Not Ready for Inspection PAUL BAZERKANIAN
Drywall Nailing 4/21/2025 Partial Approval PAUL BAZERKANIAN
Light Gage Steel Frame 4/21/2025 Partial Approval PAUL BAZERKANIAN
Light Gage Steel Frame 4/23/2025 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 4/24/2025 Partial Approval PAUL BAZERKANIAN
Light Gage Steel Frame 5/1/2025 Partial Approval PAUL BAZERKANIAN
T-Bar Ceiling 5/1/2025 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 5/2/2025 Partial Approval PAUL BAZERKANIAN
Pre-Inspection 5/30/2025 Partial Approval PAUL BAZERKANIAN
Pre-Inspection 6/5/2025 Partial Approval PAUL BAZERKANIAN
Final 6/23/2025 Permit Finaled PAUL BAZERKANIAN
Green Building Final 6/23/2025 Approved PAUL BAZERKANIAN
SGSOV-Seismic Gas S/O Valve 6/23/2025 SGSOV Approved PAUL BAZERKANIAN
Smoke Detectors 6/23/2025 Approved PAUL BAZERKANIAN