15503 S DENVER AVE 90248
Certificate Information: 15503 S DENVER AVE 90248
- Application / Permit
- 24016-10000-29518
- Plan Check / Job No.
- B24LA22878
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 1/6/2025
- Issuing Office
- Current Status
- CofO Issued on 8/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/20/2024 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 9/21/2024 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 10/17/2024 | GURUNATH NESARAJAH |
| Plan Check Approved | 12/23/2024 | GURUNATH NESARAJAH |
| Issued | 1/6/2025 | APPLICANT |
| CofO in Progress | 8/20/2025 | BEN MOLSTAD |
| Permit Finaled | 8/21/2025 | ANSON MAGLASANG |
| CofO Issued | 8/21/2025 | ANSON MAGLASANG |
| Permit Finaled | 8/21/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 10/5/2024 | ABEL CASILLAS |
| Roof/Waste drainage to street | Cleared | 10/5/2024 | ABEL CASILLAS |
| Sewer availability | Cleared | 10/5/2024 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 10/11/2024 | ABEL CASILLAS |
| Construction near power lines | Cleared | 12/18/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/28/2025 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 2/3/2025 | Partial Approval | BEN MOLSTAD |
| Footing/Foundation/Slab | 2/7/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Footing/Foundation/Slab | 2/11/2025 | Corrections Issued | BEN MOLSTAD |
| Deputy Drilled-In Anchors | 2/18/2025 | Approved | BEN MOLSTAD |
| Footing/Foundation/Slab | 2/18/2025 | Partial Approval | BEN MOLSTAD |
| Green Building Rough | 3/17/2025 | Approved | BEN MOLSTAD |
| METHANE-Rough | 3/17/2025 | Approved | BEN MOLSTAD |
| Wood Frame | 3/17/2025 | Approved | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2025 | Approved | BEN MOLSTAD |
| Insulation | 4/18/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Insulation | 4/23/2025 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 4/23/2025 | Partial Approval | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2025 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 5/5/2025 | Partial Approval | BEN MOLSTAD |
| Interior/Exterior Lathing | 5/8/2025 | Approved | BEN MOLSTAD |
| Drywall Nailing | 5/13/2025 | Approved | BEN MOLSTAD |
| Final | 7/29/2025 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 7/29/2025 | Not Ready for Inspection | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 7/29/2025 | SGSOV Not Ready | BEN MOLSTAD |
| Smoke Detectors | 7/29/2025 | Approved | BEN MOLSTAD |
| Final | 8/14/2025 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 8/14/2025 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 8/14/2025 | SGSOV Approved | BEN MOLSTAD |
| Final | 8/20/2025 | OK to Issue CofO | BEN MOLSTAD |