1530 W 255TH ST 90710
Certificate Information: 1530 W 255TH ST 90710
- Application / Permit
- 24016-10000-29363
- Plan Check / Job No.
- B24LA22664
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. Convert detached garage to accessory dwelling unit per state law.
- Permit Issued
- Issued on 12/16/2024
- Issuing Office
- Current Status
- CofO Issued on 11/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/20/2024 | DANIEL SMILEY |
| Corrections Issued | 9/23/2024 | DANIEL SMILEY |
| Plan Check Approved | 10/25/2024 | ADAM HEGAZI |
| Issued | 12/16/2024 | APPLICANT |
| CofO in Progress | 8/20/2025 | KELLY WARNER |
| Permit Finaled | 11/18/2025 | CLAUDIO MORENO |
| CofO Issued | 11/18/2025 | CLAUDIO MORENO |
| Permit Finaled | 11/18/2025 | CLAUDIO MORENO |
Permit Application Clearance Information
| Address approval | Cleared | 9/30/2024 | XOCHITL ARQUIETA |
| ZA Case | Cleared | 10/2/2024 | DANIEL CORONADO |
| Eng Process Fee Ord 176,300 | Cleared | 10/10/2024 | XOCHITL ARQUIETA |
| Sewer availability | Cleared | 10/10/2024 | XOCHITL ARQUIETA |
Contact Information
| Contractor | Next Level Home Improvements; Lic. No.: 1120800-B | , |
Inspector Information
| KELLY WARNER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL BECKER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| KEITH EDGHILL, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GONZALEZ, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/19/2024 | Corrections Issued | PAUL REECE |
| PLUMBING-Rough | 12/19/2024 | Approved | PAUL REECE |
| Underground Mechanical | 12/19/2024 | Approved | PAUL REECE |
| Footing/Foundation/Slab | 1/14/2025 | Approved | PAUL REECE |
| BUILDING-Rough-Frame | 2/27/2025 | Approved | PAUL REECE |
| ELECTRICAL-Rough | 2/27/2025 | Approved | PAUL REECE |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2025 | Approved | PAUL REECE |
| Green Building Rough | 2/27/2025 | Approved | PAUL REECE |
| HVAC-Rough | 2/27/2025 | Approved | PAUL REECE |
| METHANE-Rough | 2/27/2025 | Approved | PAUL REECE |
| PLUMBING-Rough | 2/27/2025 | Approved | PAUL REECE |
| Insulation | 3/5/2025 | Approved | KELLY WARNER |
| Interior/Exterior Lathing | 3/5/2025 | Approved | KELLY WARNER |
| Drywall Nailing | 3/18/2025 | Approved | KELLY WARNER |
| Gas Test | 3/18/2025 | Not Ready for Inspection | KELLY WARNER |
| Interior/Exterior Lathing | 3/18/2025 | Approved | KELLY WARNER |
| Sewer | 3/18/2025 | Approved | KELLY WARNER |
| Shower Pan | 3/18/2025 | Approved | KELLY WARNER |
| Service/Power Release | 6/16/2025 | Not Ready for Inspection | KELLY WARNER |
| Final | 8/11/2025 | Corrections Issued | KELLY WARNER |
| Green Building Final | 8/11/2025 | Approved | KELLY WARNER |
| SGSOV-Seismic Gas S/O Valve | 8/11/2025 | SGSOV Not Ready | KELLY WARNER |
| Smoke Detectors | 8/11/2025 | Approved | KELLY WARNER |
| Final | 8/14/2025 | OK to Issue CofO | KELLY WARNER |
| SGSOV-Seismic Gas S/O Valve | 8/14/2025 | SGSOV Approved | KELLY WARNER |