3031 E ISABEL DR 90065
Certificate Information: 3031 E ISABEL DR 90065
- Application / Permit
- 24016-10000-29070
- Plan Check / Job No.
- B24LA22222
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ADU 368 SQ. FT. fire sprinkler- NFPA-13D GOV'T CODE SECTION 65852.2(e)(1)(A) & LAMC -12.22A33
- Permit Issued
- Issued on 12/5/2024
- Issuing Office
- Metro
- Current Status
- Issued on 12/5/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2024 | SAM CHANG |
| Corrections Issued | 9/23/2024 | SAM CHANG |
| Quality Review Completed | 9/24/2024 | EUGENE BARBEAU |
| Building Plans Picked Up | 10/2/2024 | APPLICANT |
| Applicant returned to address corrections | 10/25/2024 | SAM CHANG |
| Plan Check Approved | 10/29/2024 | SAM CHANG |
| Issued | 12/5/2024 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/7/2024 | ALEXANDER HELFER |
| Sewer availability | Cleared | 10/9/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/10/2024 | DAVID LOPEZ |
| Address approval | Cleared | 10/16/2024 | DAVID LOPEZ |
| Specific Plan | Cleared | 10/28/2024 | ANDREA MAGANA-WITHERS |
Contact Information
| Contractor | Legacy Builders & Remodeling Inc; Lic. No.: 1046784-B | 9507 DORK ST PICO RIVERA, CA 90660 |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/17/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 12/20/2024 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 12/31/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 1/16/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 4/7/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 4/7/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 4/7/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 4/7/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 4/7/2025 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 4/7/2025 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 4/14/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 4/14/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 4/14/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 4/14/2025 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 4/23/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 4/23/2025 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 4/23/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 4/29/2025 | Corrections Issued | ANTHONY RAMOS |
| Insulation | 5/16/2025 | Partial Approval | REGINA MENDEZ |
| Interior/Exterior Lathing | 5/16/2025 | Approved | REGINA MENDEZ |
| Shower Pan | 5/16/2025 | Approved | REGINA MENDEZ |
| Drywall Nailing | 5/21/2025 | Not Ready for Inspection | REGINA MENDEZ |
| Drywall Nailing | 5/22/2025 | Approved | ANTHONY RAMOS |
| Insulation | 5/22/2025 | Approved | ANTHONY RAMOS |
| Underground Mechanical | 6/24/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 8/7/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 8/7/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 8/7/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 8/7/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 8/7/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 8/7/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 8/7/2025 | Approved | ALIZAH MAYAGOITIA |