122-124 N AVENUE 63 90042

Certificate Information: 122-124 N AVENUE 63 90042

Application / Permit
24016-10000-28867
Plan Check / Job No.
B24LA21931
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT PORTION (SECOND LEVEL AND ATTIC) OF (E) TWO STORY BUILDING - STORAGE (SECOND LEVEL) AND THREE CAR GARAGE (FIRST LEVEL) ATTACHED WITH AN ADU - INTO A SINGLE FAMILY DWELLING AT THE REAR OF THE LOT TO BECOME A 3-STORY SFD W/ ATTACHED THREE CAR GARAGE AND ADU (TWO LEVELS)
Permit Issued
Issued on 7/11/2025
Issuing Office
Current Status
CofO Issued on 10/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/10/2024 APPLICANT
Assigned to Plan Check Engineer 9/19/2024 SERGIO GUTIERREZ
Corrections Issued 9/30/2024 SERGIO GUTIERREZ
Quality Review Completed 10/1/2024 RODOLFO ARIAS
Applicant returned to address corrections 11/8/2024 SERGIO GUTIERREZ
Applicant returned to address corrections 2/20/2025 SERGIO GUTIERREZ
Plan Check Approved 7/10/2025 SERGIO GUTIERREZ
Issued 7/11/2025 APPLICANT
CofO in Progress 10/1/2025 DAVID WILLIAMS
No Progress 10/4/2025 DEROLD HAUFF
CofO in Progress 10/4/2025 DEROLD HAUFF
No Progress 10/9/2025 DEROLD HAUFF
CofO in Progress 10/9/2025 DEROLD HAUFF
Permit Finaled 10/9/2025 DEROLD HAUFF
CofO Issued 10/9/2025 DEROLD HAUFF
Permit Finaled 10/9/2025 DEROLD HAUFF

Permit Application Clearance Information

"Q" conditions Cleared 10/2/2024 MAYELA VILLA
CPC Cleared 10/2/2024 MAYELA VILLA
Miscellaneous Cleared 10/2/2024 MAYELA VILLA
Miscellaneous Cleared 10/2/2024 MAYELA VILLA
Address approval Cleared 10/4/2024 STEVEN JIN
Roof/Waste drainage to street Cleared 10/4/2024 STEVEN JIN
Sewer availability Cleared 10/4/2024 STEVEN JIN
Eng Process Fee Ord 176,300 Cleared 10/7/2024 DAVID LOPEZ
HPOZ Cleared 11/5/2024 NATHALY DE LA PAZ
Hydrant and Access approval Cleared 1/8/2025 JOHN CONNEALLY
Grading Pre-Inspection Cleared 6/30/2026 MICHAEL TEMPLE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 8/26/2025 Approved DAVID WILLIAMS
ELECTRICAL-Rough 8/26/2025 Approved DAVID WILLIAMS
Green Building Rough 8/26/2025 Approved DAVID WILLIAMS
HVAC-Rough 8/26/2025 Corrections Issued DAVID WILLIAMS
PLUMBING-Rough 8/26/2025 Approved DAVID WILLIAMS
Drywall Nailing 9/19/2025 Approved DAVID WILLIAMS
HVAC-Final 9/19/2025 Approved DAVID WILLIAMS
Interior/Exterior Lathing 9/19/2025 Approved DAVID WILLIAMS
Shower Pan 9/19/2025 Approved DAVID WILLIAMS
Final 9/26/2025 Corrections Issued DAVID WILLIAMS
Green Building Final 9/26/2025 Approved DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 9/26/2025 SGSOV Approved DAVID WILLIAMS
Smoke Detectors 9/26/2025 Approved DAVID WILLIAMS
Final 10/1/2025 OK to Issue CofO DAVID WILLIAMS