910 S STANLEY AVE 90036
Certificate Information: 910 S STANLEY AVE 90036
- Application / Permit
- 24016-10000-28862
- Plan Check / Job No.
- B24LA21927
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GC 66323(a)(1).
- Permit Issued
- Issued on 9/5/2025
- Issuing Office
- Current Status
- CofO Issued on 1/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2024 | DANIEL ABRAMYAN |
| Corrections Issued | 9/14/2024 | DANIEL ABRAMYAN |
| Plan Check Approved | 9/4/2025 | ISIS ARGUETA |
| Issued | 9/5/2025 | APPLICANT |
| CofO in Progress | 1/6/2026 | RONNIE MINDANAO |
| Permit Finaled | 1/9/2026 | DEROLD HAUFF |
| Permit Finaled | 1/9/2026 | DEROLD HAUFF |
| CofO Issued | 1/9/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 10/2/2024 | ERIK VAN BREENE |
| Address approval | Cleared | 10/3/2024 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2024 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 10/3/2024 | ANTHONY MAINEZ |
| Construction near power lines | Cleared | 4/11/2025 | ENRIQUE ACOSTA |
Contact Information
| Contractor | Jinchi Construction Inc; Lic. No.: 1070360-B | , |
| Engineer | Desai,, Anil T; Lic. No.: C24653 | 1530 VIA LOS COYOTES LA HABRA, CA 90631 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/9/2025 | Conditional Approval | RONNIE MINDANAO |
| Footing/Foundation/Slab | 9/9/2025 | Corrections Issued | RONNIE MINDANAO |
| Footing/Foundation/Slab | 9/10/2025 | Corrections Issued | RONNIE MINDANAO |
| Footing/Foundation/Slab | 9/12/2025 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 9/19/2025 | Approved | RONNIE MINDANAO |
| Sewer | 9/19/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 10/15/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Rough | 10/15/2025 | Approved | RONNIE MINDANAO |
| Green Building Rough | 10/15/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| HVAC-Rough | 10/15/2025 | Corrections Issued | RONNIE MINDANAO |
| METHANE-Rough | 10/15/2025 | Approved | RONNIE MINDANAO |
| Sewer | 10/15/2025 | Approved | RONNIE MINDANAO |
| Shower Pan | 10/15/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 10/21/2025 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2025 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 10/21/2025 | Corrections Issued | BRENDAN MORELLI |
| Insulation | 10/24/2025 | Corrections Issued | RONNIE MINDANAO |
| Interior/Exterior Lathing | 10/24/2025 | Approved | RONNIE MINDANAO |
| Insulation | 10/28/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 10/31/2025 | Approved | RONNIE MINDANAO |
| Green Building Rough | 10/31/2025 | Approved | RONNIE MINDANAO |
| Final | 12/4/2025 | Corrections Issued | RONNIE MINDANAO |
| Green Building Final | 12/4/2025 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 12/4/2025 | SGSOV Not Ready | RONNIE MINDANAO |
| Smoke Detectors | 12/4/2025 | Approved | RONNIE MINDANAO |
| Final | 12/12/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 12/12/2025 | SGSOV Approved | RONNIE MINDANAO |
| Final | 12/19/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 12/26/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 1/5/2026 | OK to Issue CofO | RONNIE MINDANAO |