14733-14735 W LEMAY ST 91405

Certificate Information: 14733-14735 W LEMAY ST 91405

Application / Permit
24016-10000-28854
Plan Check / Job No.
B24LA21915
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE AND STORAGE CLOSET TO A JUNIOR ACCESSORY DWELLING UNIT PER STATE LAW . STORAGE CLOSET CONVERTED TO LAUNDRY CLOSET WITHIN JADU .
Permit Issued
Issued on 11/19/2024
Issuing Office
Valley
Current Status
CofO Issued on 10/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/10/2024 APPLICANT
Assigned to Plan Check Engineer 9/12/2024 MINA HABILI
Corrections Issued 9/13/2024 MINA HABILI
Building Plans Picked Up 9/17/2024 APPLICANT
Plan Check Approved 11/12/2024 GEORGE ALVAREZ
Issued 11/19/2024 APPLICANT
CofO in Progress 10/7/2025 RYAN SALAZAR
CofO Issued 10/7/2025 RUBEN SALAS
Permit Finaled 10/7/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/19/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 9/19/2024 RYAN CASTRO
Sewer availability Cleared 9/19/2024 RYAN CASTRO

Contact Information

Architect Hovsepyan,, Ara; Lic. No.: C39097 611 N BRAND BLVD #1300      GLENDALE, CA 91203
Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/16/2025 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 4/17/2025 Approved RYAN SALAZAR
PLUMBING-Rough 5/7/2025 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 6/3/2025 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 6/3/2025 Approved RYAN SALAZAR
HVAC-Rough 6/3/2025 Approved RYAN SALAZAR
PLUMBING-Rough 6/3/2025 Approved RYAN SALAZAR
BUILDING-Rough-Frame 6/6/2025 Approved RYAN SALAZAR
Green Building Rough 6/6/2025 Approved RYAN SALAZAR
Insulation 6/6/2025 Approved RYAN SALAZAR
Shower Pan 6/6/2025 Approved RYAN SALAZAR
Drywall Nailing 7/1/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 7/1/2025 Approved LOUIS ESCOTO
Final 9/30/2025 Corrections Issued RYAN SALAZAR
Green Building Final 9/30/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 9/30/2025 SGSOV Approved RYAN SALAZAR
Smoke Detectors 9/30/2025 Approved RYAN SALAZAR
Final 10/6/2025 OK to Issue CofO RYAN SALAZAR