722-722 1/8 N ECHO PARK AVE 90026
Certificate Information: 722-722 1/8 N ECHO PARK AVE 90026
- Application / Permit
- 24016-10000-28707
- Plan Check / Job No.
- B24LA21725
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: CONVERT (E) STORAGE AREA TO ACCESSORY DWELLING UNIT PER GC 66323(a)(3)
- Permit Issued
- Issued on 2/14/2025
- Issuing Office
- Current Status
- CofO Issued on 2/27/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2024 | PINANK PATEL |
| Corrections Issued | 9/13/2024 | PINANK PATEL |
| Applicant returned to address corrections | 1/10/2025 | OMAR GARNICA |
| Applicant returned to address corrections | 2/5/2025 | OMAR GARNICA |
| Plan Check Approved | 2/13/2025 | OMAR GARNICA |
| Issued | 2/14/2025 | APPLICANT |
| CofO in Progress | 2/20/2026 | HAMIK HARTOUNIAN |
| No Progress | 2/23/2026 | DEROLD HAUFF |
| CofO in Progress | 2/23/2026 | DEROLD HAUFF |
| Permit Finaled | 2/27/2026 | DEROLD HAUFF |
| CofO Issued | 2/27/2026 | DEROLD HAUFF |
| Permit Finaled | 2/27/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/25/2024 | AMBER CAMPBELL |
| Sewer availability | Cleared | 11/25/2024 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 11/27/2024 | AMBER CAMPBELL |
| HPOZ | Cleared | 12/24/2024 | SUKI GERSHENHORN |
| ZI | Cleared | 12/24/2024 | SUKI GERSHENHORN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/30/2025 | Partial Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 7/31/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| METHANE-Rough | 7/31/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Wood Frame | 7/31/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 8/8/2025 | No Access for Inspection | OSVALDO PARAMO |
| METHANE-Rough | 8/8/2025 | No Access for Inspection | OSVALDO PARAMO |
| Wood Frame | 8/8/2025 | No Access for Inspection | OSVALDO PARAMO |
| Green Building Rough | 8/21/2025 | No Access for Inspection | HAMIK HARTOUNIAN |
| METHANE-Rough | 8/21/2025 | No Access for Inspection | FREDDIE RIVERA |
| Wood Frame | 8/21/2025 | No Access for Inspection | FREDDIE RIVERA |
| Green Building Rough | 8/27/2025 | Approved | HAMIK HARTOUNIAN |
| METHANE-Rough | 8/27/2025 | Approved | HAMIK HARTOUNIAN |
| Wood Frame | 8/27/2025 | Approved | HAMIK HARTOUNIAN |
| Insulation | 9/25/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 10/9/2025 | Approved | DEVON JACKSON |
| Final | 1/15/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 1/15/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 1/15/2026 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 1/15/2026 | Approved | HAMIK HARTOUNIAN |
| Final | 2/19/2026 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Green Building Final | 2/19/2026 | Approved | HAMIK HARTOUNIAN |