2029 S CENTURY PARK EAST 1900N-2000N 90067
Certificate Information: 2029 S CENTURY PARK EAST 1900N-2000N 90067
- Application / Permit
- 24016-10000-28701
- Plan Check / Job No.
- B24LA21712
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- Eplan Office T.I. including new non-load bearing partitions, ceiling, finishes, and millwork. New internal convience stair. New gender neutral restroom. Make new opening on slab between 19th and 20th floor Area of work: 14,085 s.f.
- Permit Issued
- Issued on 1/10/2025
- Issuing Office
- Current Status
- Permit Finaled on 10/25/2025
Permit Application Status History
| Submitted | 9/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2024 | MICHAEL LOPEZ |
| Assigned to Zoning Architect | 9/12/2024 | JASON BRAVO |
| Corrections Issued | 9/30/2024 | MICHAEL LOPEZ |
| Quality Review Completed | 10/2/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 11/8/2024 | MICHAEL LOPEZ |
| Plan Check Approved | 1/3/2025 | MICHAEL LOPEZ |
| Issued | 1/10/2025 | APPLICANT |
| Permit Finaled | 10/24/2025 | RICARDO ROBLES |
Permit Application Clearance Information
| Miscellaneous | Cleared | 10/7/2024 | JACQUELINE TORRES |
| Miscellaneous | Cleared | 10/7/2024 | JACQUELINE TORRES |
| Fire Marshal Fire Life Safety | Cleared | 11/13/2024 | FIRE DEPARTMENT |
| Green Code | Cleared | 11/15/2024 | Luke Gonzales |
| DAS Clearance | Cleared | 12/12/2024 | ELIZABETH TOMS |
| Zoning Plan Check | Cleared | 12/30/2024 | Luke Gonzales |
| Hold | Cleared | 6/10/2025 | MARIA VENDIVIL |
Contact Information
| Architect | Mangan,, Andrew T; Lic. No.: C26626 | 2314 28TH STREET #6 SANTA MONICA, CA 90405 |
| Contractor | Hitt Contracting Inc; Lic. No.: 811478-B | , |
| Engineer | Stewart,, Joseph E; Lic. No.: S3065 | 4117 MEADOW LARK DR CALABASAS, CA 91302 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 7/28/2025 | Partial Approval | RICARDO ROBLES |
| Insulation | 7/31/2025 | Approved | RICARDO ROBLES |
| Drywall Nailing | 8/1/2025 | Partial Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 8/1/2025 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 8/4/2025 | Partial Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 8/14/2025 | Approved | RICARDO ROBLES |
| Structural Steel Frame | 8/14/2025 | Approved | RICARDO ROBLES |
| Drywall Nailing | 8/25/2025 | Partial Approval | RICARDO ROBLES |
| T-Bar Ceiling | 9/2/2025 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 9/5/2025 | Partial Approval | CASIMIR BRITTON |
| Drywall Nailing | 9/9/2025 | Approved | RICARDO ROBLES |
| T-Bar Ceiling | 9/15/2025 | Partial Approval | RICARDO ROBLES |
| Interior/Exterior Lathing | 9/30/2025 | Approved | RICARDO ROBLES |
| Final | 10/17/2025 | Not Ready for Inspection | RICARDO ROBLES |
| Green Building Final | 10/17/2025 | Approved | RICARDO ROBLES |
| SGSOV-Seismic Gas S/O Valve | 10/17/2025 | SGSOV Not Ready | RICARDO ROBLES |
| Smoke Detectors | 10/17/2025 | Not Ready for Inspection | RICARDO ROBLES |
| Final | 10/24/2025 | Permit Finaled | RICARDO ROBLES |
| SGSOV-Seismic Gas S/O Valve | 10/24/2025 | SGSOV Approved | RICARDO ROBLES |
| Smoke Detectors | 10/24/2025 | Approved | RICARDO ROBLES |