2029 S CENTURY PARK EAST 1900N 90067
Certificate Information: 2029 S CENTURY PARK EAST 1900N 90067
- Application / Permit
- 24016-10000-28691
- Plan Check / Job No.
- B24LA21687
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- TENANT IMPROVEMENT TO (E) OFFICE SPACE
- Permit Issued
- Issued on 11/5/2024
- Issuing Office
- Current Status
- Permit Finaled on 8/11/2025
Permit Application Status History
| Submitted | 9/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/11/2024 | SERGIO MUNIZ |
| Corrections Issued | 9/12/2024 | SERGIO MUNIZ |
| Applicant returned to address corrections | 11/1/2024 | SERGIO MUNIZ |
| Plan Check Approved | 11/5/2024 | SERGIO MUNIZ |
| Issued | 11/5/2024 | APPLICANT |
| Permit Finaled | 8/11/2025 | RICARDO ROBLES |
Permit Application Clearance Information
| Miscellaneous | Cleared | 10/3/2024 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 10/3/2024 | JAZMIN ROQUE |
| Specific Plan | Cleared | 10/3/2024 | JAZMIN ROQUE |
| ZA Case | Cleared | 10/3/2024 | JAZMIN ROQUE |
| Fire Marshal Fire Life Safety | Cleared | 10/23/2024 | MENOA AGHAJANI |
Contact Information
| Architect | Mangan,, Andrew T; Lic. No.: C26626 | 2314 28TH STREET #6 SANTA MONICA, CA 90405 |
| Contractor | Hitt Contracting Inc; Lic. No.: 811478-B | , |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 1/9/2025 | Not Ready for Inspection | GRANT WOODS |
| Drywall Nailing | 1/10/2025 | Partial Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 1/10/2025 | Partial Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 1/13/2025 | Not Ready for Inspection | RICARDO ROBLES |
| Light Gage Steel Frame | 1/15/2025 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 1/24/2025 | Partial Inspection | RICARDO ROBLES |
| Light Gage Steel Frame | 1/30/2025 | Partial Approval | RICARDO ROBLES |
| Deputy Drilled-In Anchors | 2/6/2025 | Conditional Approval | RICARDO ROBLES |
| Deputy Steel/Welding | 2/6/2025 | Conditional Approval | RICARDO ROBLES |
| Deputy Drilled-In Anchors | 2/7/2025 | Conditional Approval | RICARDO ROBLES |
| Deputy Steel/Welding | 2/7/2025 | Conditional Approval | RICARDO ROBLES |
| Drywall Nailing | 2/7/2025 | Partial Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 2/7/2025 | Partial Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 2/20/2025 | Partial Approval | RICARDO ROBLES |
| Structural Steel Frame | 2/20/2025 | Partial Approval | RICARDO ROBLES |
| Deputy Drilled-In Anchors | 2/27/2025 | Conditional Approval | AMANUEL BERHE |
| Deputy Steel/Welding | 2/27/2025 | Conditional Approval | AMANUEL BERHE |
| Light Gage Steel Frame | 3/3/2025 | Partial Approval | RICARDO ROBLES |
| Structural Steel Frame | 3/3/2025 | Not Ready for Inspection | RICARDO ROBLES |
| Drywall Nailing | 3/4/2025 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 3/6/2025 | Partial Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 3/6/2025 | Partial Approval | RICARDO ROBLES |
| Deputy Fireproofing | 3/10/2025 | Conditional Approval | RICARDO ROBLES |
| Structural Steel Frame | 3/11/2025 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 3/13/2025 | Partial Approval | RICARDO ROBLES |
| Deputy Fireproofing | 3/17/2025 | Conditional Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 3/20/2025 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 3/24/2025 | Partial Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 3/24/2025 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 3/26/2025 | Partial Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 4/2/2025 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 4/7/2025 | Partial Approval | RICARDO ROBLES |
| T-Bar Ceiling | 4/8/2025 | Not Ready for Inspection | RICARDO ROBLES |
| T-Bar Ceiling | 4/10/2025 | Partial Inspection | RICARDO ROBLES |
| T-Bar Ceiling | 4/14/2025 | Partial Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 4/16/2025 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 4/21/2025 | Partial Approval | DERRICK SPENCER |
| Final | 5/13/2025 | Partial Approval | RICARDO ROBLES |
| Green Building Final | 5/13/2025 | Approved | RICARDO ROBLES |
| SGSOV-Seismic Gas S/O Valve | 5/13/2025 | SGSOV Approved | RICARDO ROBLES |
| Smoke Detectors | 5/13/2025 | Approved | RICARDO ROBLES |
| Final | 5/15/2025 | Partial Inspection | RICARDO ROBLES |
| Green Building Rough | 5/19/2025 | Partial Approval | RICARDO ROBLES |
| Deputy Drilled-In Anchors | 6/30/2025 | Conditional Approval | RICARDO ROBLES |
| Deputy Steel/Welding | 6/30/2025 | Conditional Approval | RICARDO ROBLES |
| Deputy Drilled-In Anchors | 7/1/2025 | Conditional Approval | RICARDO ROBLES |
| Deputy Steel/Welding | 7/1/2025 | Conditional Approval | RICARDO ROBLES |
| Deputy Steel/Welding | 7/9/2025 | Conditional Approval | RICARDO ROBLES |
| Deputy Steel/Welding | 7/10/2025 | Conditional Approval | RICARDO ROBLES |
| Final | 8/5/2025 | Not Ready for Inspection | RICARDO ROBLES |
| Final | 8/11/2025 | Permit Finaled | RICARDO ROBLES |