3103 W 15TH ST 90019
Certificate Information: 3103 W 15TH ST 90019
- Application / Permit
- 24016-10000-28627
- Plan Check / Job No.
- B24LA21622
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan : Soft-Story Seismic Retrofit per LABC Chapter 93: INSTALL (N)-(1) SPECIAL CANTILEVERED COLUMN WITH GRADE BEAM
- Permit Issued
- Issued on 3/25/2025
- Issuing Office
- Current Status
- CofC Issued on 6/9/2025
Permit Application Status History
| Submitted | 9/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2024 | BIDYUT RATH |
| Corrections Issued | 9/26/2024 | BIDYUT RATH |
| Quality Review Completed | 10/8/2024 | HANS SANTIAGO |
| Applicant returned to address corrections | 10/22/2024 | BIDYUT RATH |
| Applicant returned to address corrections | 10/24/2024 | BIDYUT RATH |
| Applicant returned to address corrections | 1/22/2025 | BIDYUT RATH |
| Applicant returned to address corrections | 1/23/2025 | BIDYUT RATH |
| Plan Check Approved | 1/30/2025 | BIDYUT RATH |
| Issued | 3/25/2025 | APPLICANT |
| OK for CofC | 6/9/2025 | DARRYL ARNOLD |
| CofC Issued | 6/9/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 3/25/2025 | KORNEL LELEA |
Contact Information
| Contractor | Titan Contracting Services Inc; Lic. No.: 976552-B | 13434 RAYMER STREET NORTH HOLLYWOOD, CA 91605 |
| Engineer | Ding,, Wenzhuo; Lic. No.: C82891 | 5205 SUNNY POINT PL RANCHO PALOS VERDES, CA 90275 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/16/2025 | Corrections Issued | DARRYL ARNOLD |
| Wood Frame | 4/16/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 4/18/2025 | Conditional Approval | DARRYL ARNOLD |
| Drywall Nailing | 4/22/2025 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 4/22/2025 | Approved | DARRYL ARNOLD |
| Final | 4/28/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 4/28/2025 | Conditional Approval | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 4/28/2025 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 4/28/2025 | Conditional Approval | DARRYL ARNOLD |
| Final | 6/9/2025 | OK for CofC | DARRYL ARNOLD |
| METHANE-Final | 6/9/2025 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 6/9/2025 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 6/9/2025 | Approved | DARRYL ARNOLD |