8406 W MELROSE PL 90069

Certificate Information: 8406 W MELROSE PL 90069

Application / Permit
24016-10000-28591
Plan Check / Job No.
B24LA21581
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
[ePlan] Tenant improvement to create a new retail space from existing mixed use commercial building (1912sf). Scope includes new partitions, ceiling, lighting, air distribution; new floor coverings and wall finishes; new sales area display and millwork fixtures; and new millwork and kitchenette in back of house area.
Permit Issued
Issued on 11/8/2024
Issuing Office
Current Status
CofO in Progress on 12/3/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/9/2024 APPLICANT
Assigned to Plan Check Engineer 9/13/2024 RICARDO RAMIREZ
Corrections Issued 9/16/2024 RICARDO RAMIREZ
Applicant returned to address corrections 10/30/2024 RICARDO RAMIREZ
Plan Check Approved 11/6/2024 RICARDO RAMIREZ
Issued 11/8/2024 APPLICANT
CofO in Progress 12/3/2025 MARTIN TAVITIAN

Permit Application Clearance Information

Address approval Cleared 10/15/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 11/6/2024 JUSTIN BICOL

Contact Information

Architect Bonvicini,, Pierluigi; Lic. No.: NA17303       ,
Contractor Ferrante Koberling Construction Inc; Lic. No.: 988562-B       ,

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Insulation 1/7/2025 Not Ready for Inspection MARTIN TAVITIAN
Light Gage Steel Frame 1/7/2025 Conditional Approval MARTIN TAVITIAN
METHANE-Rough 1/7/2025 Approved MARTIN TAVITIAN
Pre-Inspection 1/7/2025 Approved MARTIN TAVITIAN
Excavation/Setback/Form/Re-Bar 1/22/2025 Partial Approval CHRISTOPHER BLACKWOOD
Footing/Foundation/Slab 1/22/2025 Partial Approval CHRISTOPHER BLACKWOOD
Drywall Nailing 2/4/2025 Partial Approval JEROME BLACKWOOD
Light Gage Steel Frame 2/12/2025 Approved MARTIN TAVITIAN
T-Bar Ceiling 2/12/2025 Conditional Approval MARTIN TAVITIAN
Wood Frame 2/12/2025 Approved MARTIN TAVITIAN
T-Bar Ceiling 4/4/2025 Approved MARTIN TAVITIAN
Final 4/8/2025 Not Ready for Inspection MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 4/8/2025 SGSOV Approved MARTIN TAVITIAN
Smoke Detectors 4/8/2025 No Access for Inspection MARTIN TAVITIAN
Final 4/11/2025 Conditional Approval DARRYL ARNOLD
Smoke Detectors 4/11/2025 Conditional Approval DARRYL ARNOLD
Final 4/16/2025 OK to Issue CofO MARTIN TAVITIAN
Smoke Detectors 4/16/2025 Approved MARTIN TAVITIAN