22843 W VENTURA BLVD 91364
Certificate Information: 22843 W VENTURA BLVD 91364
- Application / Permit
- 24016-10000-28454
- Plan Check / Job No.
- B24LA21422
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- CONVERT (E) RETAIL SPACE INTO OFFICE. INCLUDES NEW EXT. RAMP. (1,750 SF)
- Permit Issued
- Issued on 11/18/2024
- Issuing Office
- Current Status
- CofO Issued on 10/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/6/2024 | LAWRENCE QUIRANTE |
| Corrections Issued | 9/7/2024 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 9/10/2024 | APPLICANT |
| Applicant returned to address corrections | 10/11/2024 | JOSE VELAZQUEZ |
| Plan Check Approved | 11/18/2024 | NEHEMIAS RAMOS |
| Issued | 11/18/2024 | APPLICANT |
| CofO in Progress | 10/21/2025 | BRIAN KELLY |
| Permit Finaled | 10/22/2025 | JEFFREY DURAN |
| CofO Issued | 10/22/2025 | JEFFREY DURAN |
| Permit Finaled | 10/22/2025 | JEFFREY DURAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/22/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/25/2024 | CARLOS AGUILERA |
| "D" conditions | Cleared | 10/29/2024 | ALEX VELA |
| Specific Plan | Cleared | 11/12/2024 | ADRINEH MELKONIAN |
Contact Information
| Architect | Schneider,, Brent T; Lic. No.: C21821 | 3350 WILLOW LANE WESTLAKE VILLAGE, CA 91361 |
| Contractor | Kling Family Construction; Lic. No.: 916860-B | 1014 S WESLAKE BLVD #14-106 WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 12/13/2024 | Not Ready for Inspection | BRIAN KELLY |
| Light Gage Steel Frame | 1/13/2025 | Not Ready for Inspection | BRIAN KELLY |
| Light Gage Steel Frame | 3/18/2025 | Approved | BRIAN KELLY |
| Drywall Nailing | 3/27/2025 | Partial Inspection | BRIAN KELLY |
| Insulation | 3/27/2025 | Approved | BRIAN KELLY |
| Drywall Nailing | 4/2/2025 | Approved | BRIAN KELLY |
| T-Bar Ceiling | 5/6/2025 | Not Ready for Inspection | DEANDRE HOFFMAN |
| T-Bar Ceiling | 5/15/2025 | Conditional Approval | BRIAN KELLY |
| Interior/Exterior Lathing | 7/24/2025 | Approved | BRIAN KELLY |
| Final | 9/19/2025 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 9/19/2025 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 9/19/2025 | Not Ready for Inspection | BRIAN KELLY |
| Wood Frame | 9/19/2025 | Not Ready for Inspection | BRIAN KELLY |
| Final | 9/30/2025 | Corrections Issued | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 9/30/2025 | SGSOV Approved | BRIAN KELLY |
| Smoke Detectors | 9/30/2025 | Approved | BRIAN KELLY |
| Wood Frame | 9/30/2025 | Approved | BRIAN KELLY |
| Final | 10/21/2025 | OK to Issue CofO | BRIAN KELLY |