717 S MATEO ST 90021
Certificate Information: 717 S MATEO ST 90021
- Application / Permit
- 24016-10000-28345
- Plan Check / Job No.
- B24LA21300
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (22) Storage Building
- Work Description
- CONVERT (E) FACTORY SPACE INTO STORAGE/FACTORY/OFFICE SPACE. (E) URM BLDG. - CLASS II-A (9,800 SF)
- Permit Issued
- Issued on 12/3/2024
- Issuing Office
- Current Status
- CofO Issued on 5/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/6/2024 | LAWRENCE QUIRANTE |
| Corrections Issued | 9/7/2024 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 9/9/2024 | APPLICANT |
| Plan Check Approved | 11/25/2024 | JOHN MESIAS |
| Issued | 12/3/2024 | APPLICANT |
| CofO in Progress | 5/19/2025 | RONALD JIMENEZ |
| Permit Finaled | 5/20/2025 | RAFAEL ESPINOZA |
| CofO Issued | 5/20/2025 | RAFAEL ESPINOZA |
| Permit Finaled | 5/20/2025 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 9/12/2024 | RAFAEL FONTES |
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 10/15/2024 | WALLIE JONG |
| Specific Plan | Cleared | 11/14/2024 | YINGSHI HUANG |
| Redevelopment Project Area | Cleared | 11/15/2024 | YASMINE BASHIRI |
Contact Information
| Architect | Algaze,, Nelson; Lic. No.: C21090 | 1524 1ST STREET MANHATTAN BEACH, CA 90266 |
| Contractor | B S M Construction Inc; Lic. No.: 828014-B | 2575 STANWELL DRIVE 2ND FLOOR CONCORD, CA 94520 |
| Engineer | Breaks,, Matthew Calvin; Lic. No.: S6028 | 5056 TUJUNGA AVE APT 17 NORTH HOLLYWOOD, CA 91601 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/27/2024 | Conditional Approval | RONALD JIMENEZ |
| Footing/Foundation/Slab | 12/27/2024 | Approved | RONALD JIMENEZ |
| Interior/Exterior Lathing | 12/31/2024 | Partial Approval | RONALD JIMENEZ |
| Light Gage Steel Frame | 2/3/2025 | Approved | RONALD JIMENEZ |
| Drywall Nailing | 2/13/2025 | Partial Approval | RONALD JIMENEZ |
| Drywall Nailing | 2/25/2025 | Approved | RONALD JIMENEZ |
| Pre-Inspection | 3/21/2025 | Partial Inspection | RAMAZANALI ALMASI |
| Pre-Inspection | 4/9/2025 | Approved | RONALD JIMENEZ |
| Special/Order Compliance | 4/15/2025 | Corrections Issued | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 4/18/2025 | SGSOV Not Ready | RONALD JIMENEZ |
| Final | 5/12/2025 | Corrections Issued | RONALD JIMENEZ |
| Reinforced Masonry Frame | 5/12/2025 | Approved | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 5/12/2025 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 5/12/2025 | Approved | RONALD JIMENEZ |
| Final | 5/19/2025 | OK to Issue CofO | RONALD JIMENEZ |