1645 N NORTH MAIN ST 90012
Certificate Information: 1645 N NORTH MAIN ST 90012
- Application / Permit
- 24016-10000-28200
- Plan Check / Job No.
- B24LA21103
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- TENANT IMPROVEMENT TO AN EXISTING OFFICE BUILDING CONTAINING LIGHT TRUCK REPAIR, CAR WASH AND FUELING STATION. NO EXTERIOR ALTERATIONS.
- Permit Issued
- Issued on 2/10/2025
- Issuing Office
- Current Status
- Permit Finaled on 6/5/2025
Permit Application Status History
| Submitted | 9/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2024 | MANUEL MONTUFAR |
| Assigned to Zoning Architect | 9/5/2024 | RONALD GREENE |
| Corrections Issued | 9/9/2024 | SERGIO GUTIERREZ |
| Quality Review Completed | 9/10/2024 | RODOLFO ARIAS |
| Applicant returned to address corrections | 11/5/2024 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 12/30/2024 | MANUEL MONTUFAR |
| Plan Check Approved | 2/10/2025 | MANUEL MONTUFAR |
| Issued | 2/10/2025 | APPLICANT |
| Permit Finaled | 6/5/2025 | RONALD JIMENEZ |
Permit Application Clearance Information
| Miscellaneous | Cleared | 9/13/2024 | DAVID URITA |
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 9/30/2024 | JESSICA OPINION |
| Fire Marshal Fire Life Safety | Cleared | 1/17/2025 | WILLIAM JOHNS |
| DAS Clearance | Cleared | 2/3/2025 | ELIZABETH TOMS |
| Zoning Plan Check | Cleared | 2/4/2025 | Ronald Greene |
Contact Information
| Architect | , ; Lic. No.: C37611 | , |
| Contractor | Dgr Construction Company Inc; Lic. No.: 1010921-B | , |
| Contractor | Primus Contractors; Lic. No.: 1010921-B | , |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 2/18/2025 | Partial Approval | RONALD JIMENEZ |
| Wood Frame | 2/18/2025 | Partial Inspection | RONALD JIMENEZ |
| Excavation/Setback/Form/Re-Bar | 2/24/2025 | Approved | RONALD JIMENEZ |
| Insulation | 2/24/2025 | Partial Approval | RONALD JIMENEZ |
| Light Gage Steel Frame | 2/24/2025 | Approved | RONALD JIMENEZ |
| Drywall Nailing | 2/28/2025 | Partial Approval | RONALD JIMENEZ |
| Drywall Nailing | 3/6/2025 | Approved | RAMAZANALI ALMASI |
| Special/Order Compliance | 3/25/2025 | Approved | RONALD JIMENEZ |
| T-Bar Ceiling | 4/7/2025 | Partial Inspection | RONALD JIMENEZ |
| T-Bar Ceiling | 4/9/2025 | Partial Approval | RONALD JIMENEZ |
| Final | 6/5/2025 | Permit Finaled | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 6/5/2025 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 6/5/2025 | Approved | RONALD JIMENEZ |