20179 W RINALDI ST STE 100 91326

Certificate Information: 20179 W RINALDI ST STE 100 91326

Application / Permit
24016-10000-28198
Plan Check / Job No.
B24LA21101
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Medical Office
Work Description
Change of Use from Retail to Medical Office and TI NON-OSHPD 3.
Permit Issued
Issued on 12/9/2024
Issuing Office
Metro
Current Status
CofO Issued on 7/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/4/2024 APPLICANT
Assigned to Plan Check Engineer 9/5/2024 HERNAN ARREOLA
Assigned to Zoning Architect 9/5/2024 FRANCIS AHN
Corrections Issued 9/20/2024 HERNAN ARREOLA
Green Plans Picked Up 9/20/2024 APPLICANT
Building Plans Picked Up 9/24/2024 APPLICANT
Disabled Access Plans Picked Up 10/18/2024 APPLICANT
Quality Review Completed 11/13/2024 HERNAN ARREOLA
Applicant returned to address corrections 11/13/2024 HERNAN ARREOLA
Plan Check Approved 12/9/2024 HERNAN ARREOLA
Issued 12/9/2024 APPLICANT
TCO Issued (Expire Date: 12-30-2025) 7/3/2025 RICKEY JACKSON
CofO in Progress 7/18/2025 DEANDRE HOFFMAN
Permit Finaled 7/18/2025 JEFFREY DURAN
CofO Issued 7/18/2025 JEFFREY DURAN
Permit Finaled 7/18/2025 JEFFREY DURAN

Permit Application Clearance Information

Specific Plan Cleared 10/24/2024 MIGUEL CRISOSTOMO
"T" removal Cleared 10/28/2024 ASHLEY RODARTE
Miscellaneous Cleared 10/28/2024 ASHLEY RODARTE
Miscellaneous Cleared 10/28/2024 ASHLEY RODARTE
Miscellaneous Cleared 10/28/2024 ASHLEY RODARTE
Miscellaneous Cleared 10/28/2024 ASHLEY RODARTE
Miscellaneous Cleared 10/28/2024 ASHLEY RODARTE
Miscellaneous Cleared 10/28/2024 ASHLEY RODARTE
Specific Plan Cleared 10/30/2024 CORREY KITCHENS
Eng Process Fee Ord 176,300 Cleared 11/7/2024 CARLOS AGUILERA
Green Code Cleared 11/7/2024 AARON COSTA
Sewer availability Cleared 11/7/2024 CARLOS AGUILERA
DAS Clearance Cleared 11/15/2024 HERNAN ARREOLA
Zoning Plan Check Cleared 11/26/2024 HERNAN ARREOLA

Contact Information

Architect Borsuk,, Neal H; Lic. No.: C25618 2815 GRAYSON AVENUE      VENICE, CA 90291
Contractor Parker Brown Inc; Lic. No.: 689613-B 21116 VANOWEN STREET      CANOGA PARK, CA 91303

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/9/2025 No Access for Inspection DEANDRE HOFFMAN
Footing/Foundation/Slab 1/10/2025 Approved DEANDRE HOFFMAN
Green Building Rough 2/6/2025 No Access for Inspection DEANDRE HOFFMAN
Verify Sprinkler Sign Off 2/6/2025 No Access for Inspection DEANDRE HOFFMAN
Wood Frame 2/6/2025 No Access for Inspection DEANDRE HOFFMAN
Green Building Rough 2/11/2025 Partial Inspection DEANDRE HOFFMAN
Light Gage Steel Frame 2/11/2025 Partial Approval DEANDRE HOFFMAN
Verify Sprinkler Sign Off 2/11/2025 Partial Inspection DEANDRE HOFFMAN
Drywall Nailing 2/21/2025 No Access for Inspection DEANDRE HOFFMAN
Drywall Nailing 2/25/2025 Not Ready for Inspection DEANDRE HOFFMAN
Special/Order Compliance 3/3/2025 Corrections Issued DEANDRE HOFFMAN
Green Building Rough 4/2/2025 No Access for Inspection DEANDRE HOFFMAN
Verify Sprinkler Sign Off 4/2/2025 No Access for Inspection DEANDRE HOFFMAN
Wood Frame 4/2/2025 No Access for Inspection DEANDRE HOFFMAN
Light Gage Steel Frame 4/4/2025 No Access for Inspection DEANDRE HOFFMAN
Light Gage Steel Frame 4/17/2025 No Access for Inspection DEANDRE HOFFMAN
T-Bar Ceiling 5/6/2025 Approved DEANDRE HOFFMAN
T-Bar Ceiling 5/6/2025 Off-Hour Fees Due
SGSOV-Seismic Gas S/O Valve 6/16/2025 SGSOV Not Ready DEANDRE HOFFMAN
Final 6/25/2025 No Access for Inspection DEANDRE HOFFMAN
Green Building Final 6/25/2025 No Access for Inspection DEANDRE HOFFMAN
Green Building Rough 6/25/2025 No Access for Inspection DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 6/25/2025 SGSOV Not Ready DEANDRE HOFFMAN
Smoke Detectors 6/25/2025 No Access for Inspection DEANDRE HOFFMAN
Verify Sprinkler Sign Off 6/25/2025 Not Ready for Inspection DEANDRE HOFFMAN
Wood Frame 6/25/2025 No Access for Inspection DEANDRE HOFFMAN
Final 6/27/2025 Corrections Issued GREGORY POMISH
Green Building Final 6/27/2025 Approved GREGORY POMISH
Green Building Rough 6/27/2025 Approved GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 6/27/2025 SGSOV Approved GREGORY POMISH
Smoke Detectors 6/27/2025 Approved GREGORY POMISH
Verify Sprinkler Sign Off 6/27/2025 Approved GREGORY POMISH
Wood Frame 6/27/2025 Approved GREGORY POMISH
Final 7/3/2025 OK for TCO GREGORY POMISH
Final 7/17/2025 OK to Issue CofO DEANDRE HOFFMAN