4037 W 61ST ST 90043

Certificate Information: 4037 W 61ST ST 90043

Application / Permit
24016-10000-28088
Plan Check / Job No.
B24LA20962
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL 1. REMOVE WALL BETWEEN DINING AND KITCHEN, REMODEL KITCHEN. REMODEL (E) BATHROOM (KEEP EXISTING FIXTURE LOCATION) 2. CONVERT (E) FAMILY ROOM TO MASTER BEDROOM, BUILD NEW CLOSET AND ENLARGE (E) BATHROOM. 3.REPLACE WINDOWS AND DOORS
Permit Issued
Issued on 9/16/2024
Issuing Office
Current Status
Permit Finaled on 3/21/2025

Permit Application Status History

Submitted 9/3/2024 APPLICANT
Assigned to Plan Check Engineer 9/6/2024 PINANK PATEL
Corrections Issued 9/6/2024 PINANK PATEL
Plan Check Approved 9/13/2024 PINANK PATEL
Issued 9/16/2024 APPLICANT
Permit Finaled 3/21/2025 BARRY HACHE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/10/2024 MICHAEL TEMPLE
Sewer availability Cleared 9/11/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 9/12/2024 CHRISTINA BRACO

Contact Information

Contractor Owner-Builder       ,
Engineer Baraty,, Patrick; Lic. No.: S5900 450 NORTH BRAND BLVD STE 600      GLENDALE, CA 91203

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/11/2024 No Access for Inspection AMIR NAZARIAN
Interior/Exterior Lathing 11/12/2024 Corrections Issued AMIR NAZARIAN
Pre-Inspection 11/12/2024 Not Ready for Inspection AMIR NAZARIAN
Deputy Drilled-In Anchors 11/13/2024 Approved AMIR NAZARIAN
ELECTRICAL-Rough 11/13/2024 Not Ready for Inspection AMIR NAZARIAN
Excavation/Setback/Form/Re-Bar 11/13/2024 Corrections Issued AMIR NAZARIAN
Footing/Foundation/Slab 11/13/2024 Corrections Issued AMIR NAZARIAN
HVAC-Rough 11/13/2024 Not Ready for Inspection AMIR NAZARIAN
PLUMBING-Rough 11/13/2024 Corrections Issued AMIR NAZARIAN
Excavation/Setback/Form/Re-Bar 11/19/2024 Corrections Issued AMIR NAZARIAN
PLUMBING-Rough 11/19/2024 Corrections Issued AMIR NAZARIAN
HVAC-Rough 11/21/2024 Not Ready for Inspection JOHN QUINTANILLA
PLUMBING-Rough 11/21/2024 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 11/25/2024 Not Ready for Inspection AMIR NAZARIAN
ELECTRICAL-Rough 11/25/2024 Approved AMIR NAZARIAN
HVAC-Rough 11/25/2024 Approved AMIR NAZARIAN
BUILDING-Rough-Frame 11/27/2024 Corrections Issued AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 11/27/2024 Approved AMIR NAZARIAN
Insulation 12/3/2024 Approved ALEX COLIN
Interior/Exterior Lathing 12/3/2024 Partial Approval ALEX COLIN
Shower Pan 12/6/2024 Approved NICHOLAS LOPEZ
Drywall Nailing 12/17/2024 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 1/28/2025 Not Ready for Inspection ANTHONY RAMOS
Interior/Exterior Lathing 1/29/2025 Approved ANTHONY RAMOS
Final 3/13/2025 Corrections Issued JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 3/13/2025 SGSOV Approved JOSE MACIAS
Smoke Detectors 3/13/2025 Approved JOSE MACIAS
Final 3/21/2025 Permit Finaled BARRY HACHE