3772 S SELBY AVE 90034

Certificate Information: 3772 S SELBY AVE 90034

Application / Permit
24016-10000-28025
Plan Check / Job No.
B24LA20847
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(12) Coffee Roasting
Work Description
ePlan: Change of Use from Machine Shop to Coffee Roaster . Remodel (E) Storefront, paritions, and equipment anchorage .
Permit Issued
Issued on 10/14/2025
Issuing Office
Current Status
CofO Issued on 4/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2024 APPLICANT
Assigned to Plan Check Engineer 9/11/2024 GEORGE ALVAREZ
Corrections Issued 9/12/2024 GEORGE ALVAREZ
Applicant returned to address corrections 10/12/2024 ADAM HEGAZI
Plan Check Approved 7/28/2025 ADAM HEGAZI
Issued 10/14/2025 APPLICANT
CofO in Progress 4/2/2026 FARHAD DADBIN
Permit Finaled 4/2/2026 VASIL MIHALEV
CofO Issued 4/2/2026 VASIL MIHALEV
Permit Finaled 4/2/2026 VASIL MIHALEV

Permit Application Clearance Information

Sewer availability Cleared 10/25/2024 LIAM ODONOVAN
Eng Process Fee Ord 176,300 Cleared 10/28/2024 LIAM ODONOVAN
Specific Plan Cleared 12/5/2024 JOSHUA JONES
Food Service Establishment Cleared 7/24/2025 STANLEY WING
Food establishment approval Cleared 7/28/2025 LACDHS APPROVED

Contact Information

Contractor J B C I; Lic. No.: 979172-B       ,
Engineer Yaprak,, Taskin Tolga; Lic. No.: C72927 560 31ST ST      MANHATTAN BEACH, CA 90266

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/17/2025 Partial Approval FARHAD DADBIN
Light Gage Steel Frame 12/2/2025 Partial Approval FARHAD DADBIN
Insulation 12/5/2025 Approved FARHAD DADBIN
T-Bar Ceiling 2/6/2026 Partial Approval CASIMIR BRITTON
T-Bar Ceiling 2/9/2026 Approved PAUL DAVIDSON
Final 3/31/2026 OK to Issue CofO FARHAD DADBIN
METHANE-Final 3/31/2026 Approved FARHAD DADBIN
METHANE-Rough 3/31/2026 Approved FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 3/31/2026 SGSOV Approved FARHAD DADBIN
Smoke Detectors 3/31/2026 Approved FARHAD DADBIN
Wood Frame 3/31/2026 Approved FARHAD DADBIN