7907-7909 N HESPERIA AVE 91335
Certificate Information: 7907-7909 N HESPERIA AVE 91335
- Application / Permit
- 24016-10000-27912
- Plan Check / Job No.
- B24LA20722
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel existing Single-Family Dwelling and convert Attached Garage to Junior Accessory Dwelling Unit per GCS 65852.2(e)(1)(A) AND 65852.22
- Permit Issued
- Issued on 9/24/2024
- Issuing Office
- Current Status
- CofO Issued on 7/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/6/2024 | ALEC MOUSAKHANIAN |
| Corrections Issued | 9/9/2024 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 9/23/2024 | ALEC MOUSAKHANIAN |
| Issued | 9/24/2024 | APPLICANT |
| CofO in Progress | 6/10/2025 | ARUTYUN MADATYAN |
| Permit Finaled | 7/18/2025 | DANIEL ORRANTE |
| CofO Issued | 7/18/2025 | DANIEL ORRANTE |
| Permit Finaled | 7/18/2025 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/10/2024 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 9/10/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 9/10/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 9/16/2024 | LEE GUILBEAUX |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/11/2024 | Corrections Issued | JEFFREY BULL |
| Deputy Drilled-In Anchors | 10/15/2024 | Conditional Approval | JEFFREY BULL |
| Footing/Foundation/Slab | 10/16/2024 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 10/16/2024 | Partial Approval | JEFFREY BULL |
| Underground Mechanical | 10/21/2024 | Partial Approval | JEFFREY BULL |
| ELECTRICAL-Rough | 11/25/2024 | No Access for Inspection | ARUTYUN MADATYAN |
| HVAC-Rough | 11/25/2024 | No Access for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 11/25/2024 | No Access for Inspection | ARUTYUN MADATYAN |
| Sewer | 11/25/2024 | No Access for Inspection | ARUTYUN MADATYAN |
| Underground Mechanical | 11/25/2024 | No Access for Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 12/2/2024 | Corrections Issued | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 12/2/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Rough | 12/2/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 12/2/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Sewer | 12/2/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 12/6/2024 | Corrections Issued | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2024 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 12/6/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 12/6/2024 | Approved | ARUTYUN MADATYAN |
| Sewer | 12/6/2024 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 12/17/2024 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 12/17/2024 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 12/17/2024 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 12/17/2024 | Approved | ARUTYUN MADATYAN |
| Rough-Elec/Plmb/HVAC | 12/17/2024 | Approved | ARUTYUN MADATYAN |
| Insulation | 12/20/2024 | Approved | SCOTT SOBEL |
| Shower Pan | 12/26/2024 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 12/30/2024 | Approved | SCOTT SOBEL |
| Interior/Exterior Lathing | 12/30/2024 | Approved | SCOTT SOBEL |
| PLUMBING-Rough | 4/8/2025 | Off-Hour Fees Due | |
| Final | 4/10/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 4/10/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 4/10/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 4/10/2025 | Approved | ARUTYUN MADATYAN |
| Final | 6/4/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Green Building Final | 6/4/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 6/10/2025 | Approved | ARUTYUN MADATYAN |
| Final | 6/10/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 6/10/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 6/10/2025 | Approved | ARUTYUN MADATYAN |