1017 E AMOROSO PL 90291
Certificate Information: 1017 E AMOROSO PL 90291
- Application / Permit
- 24016-10000-27868
- Plan Check / Job No.
- B24LA20641
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL AT FIRST STORY OF (E) 2-STORY SFD.
- Permit Issued
- Issued on 11/8/2024
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 1/22/2026
Permit Application Status History
| Submitted | 8/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/6/2024 | MINA HABILI |
| Corrections Issued | 9/6/2024 | MINA HABILI |
| Building Plans Picked Up | 9/10/2024 | APPLICANT |
| Plan Check Approved | 10/4/2024 | ADAM HEGAZI |
| Issued | 11/8/2024 | APPLICANT |
| Permit Finaled | 1/21/2026 | RUBEN RIVAS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Rahban Development; Lic. No.: 1089793-B | 812 N ALPINE DRIVE BEVERLY HILLS, CA 90210 |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/11/2024 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 12/12/2024 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 12/20/2024 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 12/24/2024 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 2/10/2025 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Rough | 2/10/2025 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 2/18/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 2/18/2025 | Approved | HERBERT GIRON |
| HVAC-Rough | 2/18/2025 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 2/26/2025 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 2/26/2025 | Approved | BOBBY KEY |
| Insulation | 2/26/2025 | Conditional Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 3/13/2025 | Approved | HERBERT GIRON |
| Drywall Nailing | 3/13/2025 | Not Ready for Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2025 | Approved | HERBERT GIRON |
| Drywall Nailing | 3/20/2025 | Approved | JESUS RODRIGUEZ |
| Insulation | 3/20/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 9/10/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Final | 9/10/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 9/10/2025 | SGSOV Approved | MICHAEL ALLEN |
| Smoke Detectors | 9/10/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| ELECTRICAL-Final | 1/21/2026 | Approved | RUBEN RIVAS |
| Final | 1/21/2026 | Permit Finaled | RUBEN RIVAS |
| HVAC-Final | 1/21/2026 | Approved | RUBEN RIVAS |
| PLUMBING-Final | 1/21/2026 | Approved | RUBEN RIVAS |
| Smoke Detectors | 1/21/2026 | Approved | RUBEN RIVAS |