1030 W 19TH ST 90731
Certificate Information: 1030 W 19TH ST 90731
- Application / Permit
- 24016-10000-27228
- Plan Check / Job No.
- B24LA19882
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DETACHED GARAGE TO (N) 368 SF ADU PER GCS 65852.2(e)(1)(A). ALL WORK PER ENG.
- Permit Issued
- Issued on 9/24/2024
- Issuing Office
- Current Status
- CofO Issued on 11/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2024 | LUISANGEL VALENZUELA |
| Corrections Issued | 9/3/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 9/17/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 9/20/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 9/23/2024 | LUISANGEL VALENZUELA |
| Issued | 9/24/2024 | APPLICANT |
| CofO in Progress | 11/10/2025 | JOSEPH MCGARRY |
| Permit Finaled | 11/10/2025 | ANSON MAGLASANG |
| CofO Issued | 11/10/2025 | ANSON MAGLASANG |
| Permit Finaled | 11/10/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/6/2024 | VASIL MIHALEV |
| Address approval | Cleared | 9/8/2024 | JILVER MAZARIEGOS |
| Sewer availability | Cleared | 9/8/2024 | JILVER MAZARIEGOS |
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2024 | ERIK BEASLEY |
Contact Information
| Contractor | Vaisman Construction Inc; Lic. No.: 1076712-B | , |
| Engineer | Segovia,, Felipe; Lic. No.: NA41102 | , |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/20/2025 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 5/22/2025 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Rough | 5/22/2025 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 5/22/2025 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 6/20/2025 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/23/2025 | Conditional Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 7/25/2025 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 7/25/2025 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 7/25/2025 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 7/25/2025 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 7/25/2025 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 7/31/2025 | Partial Approval | JOSEPH MCGARRY |
| Shower Pan | 7/31/2025 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 7/31/2025 | Approved | JOSEPH MCGARRY |
| Insulation | 8/22/2025 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 8/25/2025 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 8/27/2025 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 11/4/2025 | Approved | ANSON MAGLASANG |
| Final | 11/4/2025 | Corrections Issued | ANSON MAGLASANG |
| Green Building Final | 11/4/2025 | Not Ready for Inspection | ANSON MAGLASANG |
| HVAC-Final | 11/4/2025 | Approved | ANSON MAGLASANG |
| PLUMBING-Final | 11/4/2025 | Approved | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 11/4/2025 | SGSOV Approved | ANSON MAGLASANG |
| Smoke Detectors | 11/4/2025 | Approved | ANSON MAGLASANG |
| Final | 11/7/2025 | OK to Issue CofO | JOSEPH MCGARRY |
| Green Building Final | 11/7/2025 | Approved | JOSEPH MCGARRY |