1135 1/2-3/4 W 54TH ST 90037

Certificate Information: 1135 1/2-3/4 W 54TH ST 90037

Application / Permit
24016-10000-27063
Plan Check / Job No.
B24LA19467
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Alter (E) 2-story Building with SFD above attached Garage at rear of lot . Convert attached Garage at lower level to Accessory Dwelling Unit .
Permit Issued
Issued on 9/17/2025
Issuing Office
Metro
Current Status
CofO Issued on 2/22/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2024 APPLICANT
Assigned to Plan Check Engineer 8/22/2024 GEORGE ALVAREZ
Corrections Issued 8/24/2024 GEORGE ALVAREZ
Building Plans Picked Up 9/3/2024 APPLICANT
Plan Check Approved 11/25/2024 JOHN MESIAS
Issued 9/17/2025 APPLICANT
CofO in Progress 2/17/2026 SABAS ALONSO
Permit Finaled 2/22/2026 DEROLD HAUFF
CofO Issued 2/22/2026 DEROLD HAUFF
Permit Finaled 2/22/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/6/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 9/9/2024 DAVID LOPEZ
Sewer availability Cleared 9/9/2024 DAVID LOPEZ
Tenant Habitability Plan Cleared 9/11/2024 RICARDO BOHORQUEZ
Community Plan Implem. Overlay Cleared 11/20/2024 ANACANY HURTADO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/18/2025 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 10/9/2025 Approved SABAS ALONSO
HVAC-Rough 11/6/2025 Approved SABAS ALONSO
PLUMBING-Rough 11/6/2025 Approved SABAS ALONSO
BUILDING-Rough-Frame 11/12/2025 Approved SABAS ALONSO
ELECTRICAL-Rough 11/12/2025 Approved SABAS ALONSO
Green Building Rough 11/12/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 11/12/2025 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/18/2025 Approved SABAS ALONSO
Insulation 11/19/2025 Approved ANTHONY RAMOS
Drywall Nailing 11/25/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 12/9/2025 Approved ANTHONY RAMOS
Final 1/7/2026 Not Ready for Inspection JOHN QUINTANILLA
Green Building Final 1/7/2026 Not Ready for Inspection JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 1/7/2026 SGSOV Not Ready JOHN QUINTANILLA
Smoke Detectors 1/7/2026 Not Ready for Inspection JOHN QUINTANILLA
Final 1/28/2026 Corrections Issued SABAS ALONSO
Green Building Final 1/28/2026 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 1/28/2026 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 1/28/2026 Approved SABAS ALONSO
Final 2/10/2026 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 2/10/2026 SGSOV Approved SABAS ALONSO
Service/Power Release 2/10/2026 Approved SABAS ALONSO
Final 2/12/2026 OK to Issue CofO SABAS ALONSO
Service/Power Release 2/12/2026 Approved SABAS ALONSO