2312 1/2 S WEST VIEW ST 90016

Certificate Information: 2312 1/2 S WEST VIEW ST 90016

Application / Permit
24016-10000-27031
Plan Check / Job No.
B24LA19399
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A)
Permit Issued
Issued on 1/24/2025
Issuing Office
Current Status
CofO Issued on 8/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/23/2024 APPLICANT
Assigned to Plan Check Engineer 8/28/2024 GURUNATH NESARAJAH
Corrections Issued 8/28/2024 GURUNATH NESARAJAH
Applicant returned to address corrections 12/10/2024 GURUNATH NESARAJAH
Applicant returned to address corrections 12/18/2024 GURUNATH NESARAJAH
Plan Check Approved 1/22/2025 GURUNATH NESARAJAH
Issued 1/24/2025 APPLICANT
CofO in Progress 8/18/2025 JUSTIN HAWLEY
Permit Finaled 8/21/2025 DEROLD HAUFF
CofO Issued 8/21/2025 DEROLD HAUFF
Permit Finaled 8/21/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/3/2024 TREVOR QUAN
Sewer availability Cleared 9/3/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 9/4/2024 TREVOR QUAN
Construction near power lines Cleared 12/4/2024 TINA MIRANDA

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Preferred Home Builders Inc; Lic. No.: 773147-B       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/21/2025 Corrections Issued NICHOLAS LOPEZ
Footing/Foundation/Slab 2/21/2025 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Rough 2/21/2025 Not Ready for Inspection NICHOLAS LOPEZ
Underground Mechanical 2/21/2025 Conditional Approval NICHOLAS LOPEZ
Deputy Drilled-In Anchors 2/24/2025 Conditional Approval JOSH MEISTER
Sewer 2/26/2025 Not Ready for Inspection RONNIE MINDANAO
Underground Mechanical 2/28/2025 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 3/5/2025 Corrections Issued JEFFREY MEAD
BUILDING-Rough-Frame 3/14/2025 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 3/14/2025 Not Ready for Inspection ENRIQUE MIRELES
MERV13>=Rough 3/14/2025 Not Ready for Inspection ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 3/14/2025 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 3/17/2025 Approved RONNIE MINDANAO
HVAC-Rough 3/17/2025 Not Ready for Inspection RONNIE MINDANAO
PLUMBING-Rough 3/17/2025 Approved RONNIE MINDANAO
Green Building Rough 3/18/2025 Approved ENRIQUE MIRELES
Insulation 3/18/2025 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Rough 3/19/2025 Approved RONNIE MINDANAO
Insulation 3/19/2025 Partial Approval RONNIE MINDANAO
Interior/Exterior Lathing 3/19/2025 Not Ready for Inspection RONNIE MINDANAO
Shower Pan 3/19/2025 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 3/21/2025 Not Ready for Inspection ENRIQUE MIRELES
Interior/Exterior Lathing 3/21/2025 Corrections Issued ENRIQUE MIRELES
MERV13>=Rough 3/21/2025 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/25/2025 Partial Approval JOSH MEISTER
BUILDING-Rough-Frame 3/27/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 3/27/2025 Partial Approval LUIS CASTRO
Insulation 3/27/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 3/27/2025 Approved LUIS CASTRO
Drywall Nailing 4/1/2025 Approved JOSH MEISTER
SGSOV-Seismic Gas S/O Valve 5/9/2025 SGSOV Not Ready WILLIAM SIERRA
Final 5/15/2025 Not Ready for Inspection WILLIAM SIERRA
Green Building Final 5/15/2025 Not Ready for Inspection WILLIAM SIERRA
MERV13>=Final 5/15/2025 Not Ready for Inspection WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 5/15/2025 SGSOV Not Ready WILLIAM SIERRA
Smoke Detectors 5/15/2025 Not Ready for Inspection WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 6/11/2025 SGSOV Not Ready JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 6/17/2025 SGSOV Not Ready JUSTIN HAWLEY
Final 6/25/2025 Corrections Issued JUSTIN HAWLEY
Green Building Final 6/25/2025 Not Ready for Inspection JUSTIN HAWLEY
MERV13>=Final 6/25/2025 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 6/25/2025 SGSOV Not Ready JUSTIN HAWLEY
Smoke Detectors 6/25/2025 Not Ready for Inspection JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 7/23/2025 SGSOV Not Ready JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 7/28/2025 SGSOV Not Ready JUSTIN HAWLEY
Final 7/30/2025 Partial Inspection FREDDIE RIVERA
Green Building Final 7/30/2025 Partial Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 7/30/2025 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 7/30/2025 Partial Inspection FREDDIE RIVERA
Final 8/11/2025 Corrections Issued JUSTIN HAWLEY
Green Building Final 8/11/2025 Not Ready for Inspection JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 8/11/2025 SGSOV Not Ready JUSTIN HAWLEY
Smoke Detectors 8/11/2025 Not Ready for Inspection JUSTIN HAWLEY
Final 8/13/2025 Not Ready for Inspection JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 8/15/2025 SGSOV Not Ready JUSTIN HAWLEY
ELECTRICAL-Final 8/18/2025 Approved JUSTIN HAWLEY
Final 8/18/2025 OK to Issue CofO JUSTIN HAWLEY
Green Building Final 8/18/2025 Approved JUSTIN HAWLEY
HVAC-Final 8/18/2025 Approved JUSTIN HAWLEY
PLUMBING-Final 8/18/2025 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 8/18/2025 SGSOV Approved JUSTIN HAWLEY
Smoke Detectors 8/18/2025 Approved JUSTIN HAWLEY