9067 1/2 W AIRDROME ST 90035
Certificate Information: 9067 1/2 W AIRDROME ST 90035
- Application / Permit
- 24016-10000-26891
- Plan Check / Job No.
- B24LA19193
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert (E) detached garage to storage room and ADU per GCS 66323(a)(4)
- Permit Issued
- Issued on 3/14/2025
- Issuing Office
- Current Status
- Issued on 3/14/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2024 | SUNMIN LEE |
| Corrections Issued | 8/26/2024 | SUNMIN LEE |
| Applicant returned to address corrections | 1/29/2025 | MINA HABILI |
| Plan Check Approved | 2/14/2025 | LUKE GONZALES |
| Issued | 3/14/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/17/2024 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 10/17/2024 | WALLIE JONG |
| Sewer availability | Cleared | 10/17/2024 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 10/28/2024 | VASIL MIHALEV |
| Construction within easement | Cleared | 12/26/2024 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 1/28/2025 | WALLIE JONG |
Contact Information
| Contractor | Benjy West Builders Inc; Lic. No.: 1032329-B | , |
| Engineer | Crook,, Barrett Cameron; Lic. No.: C57196 | 5306 MULHOLLAND DRIVE SUMMERVILLE, SC 29485 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/3/2025 | Corrections Issued | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 4/8/2025 | Approved | EVAN COOPER |
| PLUMBING-Rough | 4/28/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 6/10/2025 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2025 | Corrections Issued | EVAN COOPER |
| Gas Test | 6/10/2025 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 6/10/2025 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 6/10/2025 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 6/18/2025 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2025 | Partial Approval | EVAN COOPER |
| Gas Test | 6/18/2025 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 6/18/2025 | Approved | EVAN COOPER |
| Insulation | 7/10/2025 | Approved | EVAN COOPER |
| Drywall Nailing | 8/18/2025 | Approved | DANIEL VERA |
| ELECTRICAL-Rough | 10/29/2025 | Corrections Issued | EVAN COOPER |
| Service/Power Release | 10/29/2025 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Final | 11/14/2025 | Corrections Issued | EVAN COOPER |
| Service/Power Release | 11/17/2025 | Approved | EVAN COOPER |