4900 W HOLLYWOOD BLVD 90027
Certificate Information: 4900 W HOLLYWOOD BLVD 90027
- Application / Permit
- 24016-10000-26830
- Plan Check / Job No.
- B24LA19059
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- TENANT IMPROVEMENT AT (E) RETAIL ON 1ST FLOOR LEVEL AND ADD TWO LEVEL HYDRAULIC LIFTS
- Permit Issued
- Issued on 12/18/2024
- Issuing Office
- Current Status
- Permit Finaled on 2/9/2026
Permit Application Status History
| Submitted | 8/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2024 | SERGIO GUTIERREZ |
| Assigned to Zoning Architect | 8/22/2024 | BENNY WONG |
| Corrections Issued | 8/27/2024 | SERGIO GUTIERREZ |
| Quality Review Completed | 8/28/2024 | RODOLFO ARIAS |
| Plan Check Approved | 12/9/2024 | SERGIO GUTIERREZ |
| Issued | 12/18/2024 | APPLICANT |
| Permit Finaled | 2/9/2026 | LUIS CCAMACHO |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2024 | JESSICA OPINION |
| Metro Rail approval | Cleared | 9/9/2024 | JENNIFER SU |
| "D" conditions | Cleared | 9/10/2024 | MAYELA VILLA |
| CPC | Cleared | 9/10/2024 | MAYELA VILLA |
| Miscellaneous | Cleared | 9/10/2024 | MAYELA VILLA |
| Miscellaneous | Cleared | 9/10/2024 | MAYELA VILLA |
| ZA Case | Cleared | 9/10/2024 | MAYELA VILLA |
| Fire Marshal Fire Life Safety | Cleared | 11/8/2024 | PEJMAN NOORI |
| DAS Clearance | Cleared | 11/12/2024 | Sergio Muniz |
| Zoning Plan Check | Cleared | 11/22/2024 | BENNY WONG |
Contact Information
| Architect | Malak,, Hany; Lic. No.: NA27490 | , |
| Contractor | J R M Construction West Llc; Lic. No.: 1013928-B | , |
| Engineer | Schroeder,, Mark; Lic. No.: S4110 | 16969 VON KARMAN AVE 240 IRVINE, CA 92606 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 2/21/2025 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 2/26/2025 | Partial Approval | LUIS CCAMACHO |
| Insulation | 2/26/2025 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 3/3/2025 | Partial Approval | LUIS CCAMACHO |
| Reinforced Concrete Frame | 3/12/2025 | Partial Approval | LUIS CCAMACHO |
| Light Gage Steel Frame | 3/17/2025 | Corrections Issued | LUIS CCAMACHO |
| Light Gage Steel Frame | 3/24/2025 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 3/27/2025 | Partial Approval | LUIS CCAMACHO |
| Reinforced Concrete Frame | 4/9/2025 | Partial Approval | MARTIN TAVITIAN |
| Light Gage Steel Frame | 6/2/2025 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 10/3/2025 | Partial Approval | DAVID BURKHEAD |
| Final | 2/5/2026 | Partial Inspection | LUIS CCAMACHO |
| SGSOV-Seismic Gas S/O Valve | 2/5/2026 | SGSOV Approved | LUIS CCAMACHO |
| Smoke Detectors | 2/5/2026 | Approved | LUIS CCAMACHO |