845-845 1/2 W 76TH ST 90044

Certificate Information: 845-845 1/2 W 76TH ST 90044

Application / Permit
24016-10000-26752
Plan Check / Job No.
B24LA18978
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT SFD INTO DUPLEX (NO SQFT ADDED) UNIT1: 577 SQFT UNIT2: 537 SQFT NO SQFT ADDED 1 OF 2
Permit Issued
Issued on 2/6/2025
Issuing Office
Metro
Current Status
CofO Issued on 1/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/20/2024 APPLICANT
Assigned to Plan Check Engineer 8/22/2024 KHUONG TRUONG
Corrections Issued 8/27/2024 KHUONG TRUONG
Quality Review Completed 8/28/2024 KEN GILL
Building Plans Picked Up 8/30/2024 APPLICANT
Applicant returned to address corrections 10/10/2024 KHUONG TRUONG
Applicant returned to address corrections 11/13/2024 KHUONG TRUONG
Plan Check Approved 2/4/2025 KHUONG TRUONG
Issued 2/6/2025 APPLICANT
CofO in Progress 1/6/2026 JOHN QUINTANILLA
Permit Finaled 1/9/2026 DEROLD HAUFF
CofO Issued 1/9/2026 DEROLD HAUFF
Permit Finaled 1/9/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/29/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 8/29/2024 DAVID LOPEZ
Roof/Waste drainage to street Cleared 8/29/2024 DAVID LOPEZ
Sewer availability Cleared 8/29/2024 DAVID LOPEZ

Contact Information

Contractor So Cal Construction Enterprises Inc; Lic. No.: 832488-B P O BOX 96      SAN GABRIEL, CA 91778
Engineer Evangelista,, Gil Viernes; Lic. No.: S2422 749 N FEATHERWOOD DR      DIAMOND BAR, CA 91765

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/14/2025 Conditional Approval JOHN QUINTANILLA
Footing/Foundation/Slab 2/14/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 3/13/2025 Corrections Issued JOHN QUINTANILLA
HVAC-Rough 3/13/2025 Approved JOHN QUINTANILLA
PLUMBING-Rough 3/13/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 3/14/2025 Partial Approval JOHN QUINTANILLA
Interior/Exterior Lathing 3/14/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 3/18/2025 Partial Approval JOHN QUINTANILLA
Insulation 3/18/2025 Partial Approval JOHN QUINTANILLA
Sewer 3/18/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 3/20/2025 Approved JOHN QUINTANILLA
Drywall Nailing 3/21/2025 Approved JOHN QUINTANILLA
Verify Rec and Parks Fee Memo 6/17/2025 Partial Inspection JOHN QUINTANILLA
BUILDING-Rough-Frame 7/15/2025 Approved JOHN QUINTANILLA
PLUMBING-Final 7/15/2025 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 7/15/2025 SGSOV Approved JOHN QUINTANILLA
Smoke Detectors 7/15/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Final 7/17/2025 Approved JOHN QUINTANILLA
HVAC-Final 7/17/2025 Partial Approval JOHN QUINTANILLA
Service/Power Release 7/17/2025 Approved JOHN QUINTANILLA
Final 8/7/2025 Conditional Approval JOHN QUINTANILLA
Final 12/22/2025 Conditional Approval JOHN QUINTANILLA
Final 1/5/2026 OK to Issue CofO JOHN QUINTANILLA