1519 N CRESCENT HEIGHTS BLVD 90046
Certificate Information: 1519 N CRESCENT HEIGHTS BLVD 90046
- Application / Permit
- 24016-10000-26677
- Plan Check / Job No.
- B24LA18875
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: Existing Rec. room above the garage plus existing 1-car garage to be converted into a 2-story ADU. Total area of proposed ADU: 529 Sq.Ft.
- Permit Issued
- Issued on 1/2/2025
- Issuing Office
- Current Status
- CofO Issued on 8/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/28/2024 | JOSE VELAZQUEZ |
| Corrections Issued | 8/29/2024 | JOSE VELAZQUEZ |
| Plan Check Approved | 11/12/2024 | NGHI SU |
| Issued | 1/2/2025 | APPLICANT |
| CofO in Progress | 2/10/2025 | ROY SPAULDING |
| Permit Finaled | 8/12/2025 | DEROLD HAUFF |
| CofO Issued | 8/12/2025 | DEROLD HAUFF |
| Permit Finaled | 8/12/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| ZA Case | Cleared | 9/4/2024 | MAYELA VILLA |
| ZA Case | Cleared | 9/4/2024 | MAYELA VILLA |
| ZA Case | Cleared | 9/4/2024 | MAYELA VILLA |
| ZA Case | Cleared | 9/4/2024 | MAYELA VILLA |
| ZA Case | Cleared | 9/4/2024 | MAYELA VILLA |
| Address approval | Cleared | 9/17/2024 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 9/17/2024 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2024 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 1/6/2025 | Not Ready for Inspection | ROY SPAULDING |
| Final | 1/6/2025 | Corrections Issued | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 1/6/2025 | SGSOV Not Ready | ROY SPAULDING |
| Smoke Detectors | 1/6/2025 | Not Ready for Inspection | ROY SPAULDING |
| BUILDING-Rough-Frame | 1/15/2025 | Approved | ROY SPAULDING |
| ELECTRICAL-Final | 1/15/2025 | Approved | ROY SPAULDING |
| Final | 1/15/2025 | Not Ready for Inspection | ROY SPAULDING |
| Footing/Foundation/Slab | 1/15/2025 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 1/15/2025 | Partial Approval | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 1/15/2025 | SGSOV Not Ready | ROY SPAULDING |
| Smoke Detectors | 1/15/2025 | Not Ready for Inspection | ROY SPAULDING |
| Drywall Nailing | 1/21/2025 | Partial Approval | ROY SPAULDING |
| BUILDING-Rough-Frame | 1/27/2025 | Not Ready for Inspection | ROY SPAULDING |
| Final | 1/27/2025 | Not Ready for Inspection | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 1/27/2025 | SGSOV Not Ready | ROY SPAULDING |
| Smoke Detectors | 1/27/2025 | Not Ready for Inspection | ROY SPAULDING |
| BUILDING-Rough-Frame | 1/29/2025 | Approved | ROY SPAULDING |
| Final | 1/29/2025 | Corrections Issued | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 1/29/2025 | SGSOV Not Ready | ROY SPAULDING |
| Smoke Detectors | 1/29/2025 | Approved | ROY SPAULDING |
| Final | 2/4/2025 | Corrections Issued | ROY SPAULDING |
| HVAC-Final | 2/4/2025 | Not Ready for Inspection | ROY SPAULDING |
| PLUMBING-Final | 2/4/2025 | Not Ready for Inspection | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 2/4/2025 | SGSOV Not Ready | ROY SPAULDING |
| Final | 2/7/2025 | OK to Issue CofO | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 2/7/2025 | SGSOV Approved | ROY SPAULDING |