3701 S BLUFF PL 90731
Certificate Information: 3701 S BLUFF PL 90731
- Application / Permit
- 24016-10000-26443
- Plan Check / Job No.
- B24LA18640
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: RETROFIT USING (2) SPECIAL STEEL CANTILEVER COLUMNS & GRADE BEAMS
- Permit Issued
- Issued on 10/3/2024
- Issuing Office
- Current Status
- CofC Issued on 1/21/2025
Permit Application Status History
| Submitted | 8/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2024 | HANS SANTIAGO |
| Corrections Issued | 8/26/2024 | HANS SANTIAGO |
| Quality Review Completed | 8/30/2024 | CHARMIE HUYNH |
| Plan Check Approved | 9/17/2024 | ANDREW SANTIAGO |
| Issued | 10/3/2024 | APPLICANT |
| OK for CofC | 1/10/2025 | MICHAEL PETRUSKO |
| CofC Issued | 1/21/2025 | MICHAEL PETRUSKO |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 10/2/2024 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Zebra Construction Inc; Lic. No.: 1055609-B | 2523 S ROBERTSON BLVD LOS ANGELES, CA 90034 |
| Engineer | Tajvidi,, Seyed Mohammad; Lic. No.: NA84559 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/2/2024 | Conditional Approval | JOEY BUCHANAN |
| Structural Steel Frame | 12/2/2024 | Conditional Approval | JOEY BUCHANAN |
| Wood Frame | 12/2/2024 | Corrections Issued | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 12/3/2024 | Conditional Approval | JOEY BUCHANAN |
| Deputy Steel/Welding | 12/3/2024 | Conditional Approval | JOEY BUCHANAN |
| Wood Frame | 12/9/2024 | Approved | JOEY BUCHANAN |
| Interior/Exterior Lathing | 12/11/2024 | Approved | JOEY BUCHANAN |
| Final | 1/8/2025 | Corrections Issued | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 1/8/2025 | SGSOV Not Ready | MICHAEL PETRUSKO |
| Smoke Detectors | 1/8/2025 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Final | 1/10/2025 | OK for CofC | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 1/10/2025 | SGSOV Approved | MICHAEL PETRUSKO |
| Smoke Detectors | 1/10/2025 | Approved | MICHAEL PETRUSKO |