11601 W MONTANA AVE 90049
Certificate Information: 11601 W MONTANA AVE 90049
- Application / Permit
- 24016-10000-26160
- Plan Check / Job No.
- B24LA18317
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (35) Condominium
- Work Description
- Replace walkway deck on the 2nd and 3rd floors with steel deck.
- Permit Issued
- Issued on 11/19/2024
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 5/7/2025
Permit Application Status History
| Submitted | 8/15/2024 | APPLICANT |
| Assigned to Zoning Architect | 8/22/2024 | SARHAD GHEVANDIAN |
| Assigned to Plan Check Engineer | 9/5/2024 | TU HUA |
| Corrections Issued | 9/11/2024 | TU HUA |
| Quality Review Completed | 9/25/2024 | KEN GILL |
| Building Plans Picked Up | 10/4/2024 | APPLICANT |
| Applicant returned to address corrections | 10/16/2024 | TU HUA |
| Plan Check Approved | 11/13/2024 | TU HUA |
| Issued | 11/19/2024 | APPLICANT |
| Permit Finaled | 5/6/2025 | CASIMIR BRITTON |
Permit Application Clearance Information
| ZI | Cleared | 10/4/2024 | MAYELA VILLA |
| Zoning Plan Check | Cleared | 11/6/2024 | SARHAD GHEVANDIAN |
Contact Information
| Contractor | New Choice Contractors; Lic. No.: 782294-B | P O BOX 6358 BEVERLY HILLS, CA 90212 |
| Engineer | Mohazzab, Hosseinian, Hossein Jon Mohazzab; Lic. No.: S3760 | 5408 W 140TH ST HAWTHORNE, CA 90250 |
Inspector Information
| CASIMIR BRITTON, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
| SHAVONNE ESPINOZA, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/21/2024 | Partial Inspection | CASIMIR BRITTON |
| Deputy Steel/Welding | 1/10/2025 | Conditional Approval | GRANT WOODS |
| Special/Order Compliance | 1/28/2025 | Corrections Issued | CASIMIR BRITTON |
| Structural Steel Frame | 1/28/2025 | Corrections Issued | CASIMIR BRITTON |
| Structural Steel Frame | 2/6/2025 | Not Ready for Inspection | CASIMIR BRITTON |
| Structural Steel Frame | 2/12/2025 | Not Ready for Inspection | CASIMIR BRITTON |
| Deputy Wood Construction | 2/18/2025 | Conditional Approval | CASIMIR BRITTON |
| Interior/Exterior Lathing | 2/21/2025 | Not Ready for Inspection | CASIMIR BRITTON |
| Light Gage Steel Frame | 2/21/2025 | Not Ready for Inspection | CASIMIR BRITTON |
| Interior/Exterior Lathing | 2/27/2025 | Partial Approval | CASIMIR BRITTON |
| Drywall Nailing | 3/4/2025 | Partial Approval | CASIMIR BRITTON |
| Interior/Exterior Lathing | 3/4/2025 | Not Ready for Inspection | CASIMIR BRITTON |
| Interior/Exterior Lathing | 3/10/2025 | Approved | CASIMIR BRITTON |
| Final | 4/21/2025 | No Access for Inspection | CASIMIR BRITTON |
| SGSOV-Seismic Gas S/O Valve | 4/21/2025 | SGSOV Not Ready | CASIMIR BRITTON |
| Smoke Detectors | 4/21/2025 | No Access for Inspection | CASIMIR BRITTON |
| Final | 5/6/2025 | Permit Finaled | CASIMIR BRITTON |
| SGSOV-Seismic Gas S/O Valve | 5/6/2025 | SGSOV Approved | CASIMIR BRITTON |
| Smoke Detectors | 5/6/2025 | Approved | CASIMIR BRITTON |