1529 N WINONA BLVD 90027

Certificate Information: 1529 N WINONA BLVD 90027

Application / Permit
24016-10000-26011
Plan Check / Job No.
B24LA18091
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ePlan: Convert (e) attached 2-car garage into an A.D.U. (345 sq.ft.) per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 11/5/2025
Issuing Office
Current Status
CofO Issued on 7/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/14/2024 APPLICANT
Assigned to Plan Check Engineer 8/16/2024 REZA HAGHIGHAT
Corrections Issued 8/16/2024 REZA HAGHIGHAT
Applicant returned to address corrections 9/12/2024 REZA HAGHIGHAT
Plan Check Approved 10/15/2024 REZA HAGHIGHAT
Issued 11/5/2025 APPLICANT
CofO in Progress 7/10/2026 CRAIG VAUGHAN
Permit Finaled 7/11/2026 DEROLD HAUFF
CofO Issued 7/11/2026 DEROLD HAUFF
Permit Finaled 7/11/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/30/2024 CELINA MORENO
Sewer availability Cleared 8/30/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 9/5/2024 CELINA MORENO
ZA Case Cleared 9/5/2024 ROSALINDA MEZA
Specific Plan Cleared 10/7/2024 NASHYA JENSEN

Contact Information

Architect Ko,, Michael Myungsoo; Lic. No.: NA22356       ,
Contractor Elm Construction; Lic. No.: 1099704-B       ,
Contractor Elm Group La Inc; Lic. No.: 1099704-B       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/2/2025 Corrections Issued CRAIG VAUGHAN
Gas Test 1/20/2026 Corrections Issued ALIZAH MAYAGOITIA
Underground Mechanical 1/20/2026 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 2/4/2026 Approved CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 2/4/2026 Not Ready for Inspection CRAIG VAUGHAN
Shower Pan 2/4/2026 Not Ready for Inspection CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 2/5/2026 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 2/11/2026 Approved CRAIG VAUGHAN
PLUMBING-Rough 2/11/2026 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 3/5/2026 Partial Approval CRAIG VAUGHAN
Insulation 3/11/2026 Partial Approval CRAIG VAUGHAN
Shower Pan 3/19/2026 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 3/25/2026 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 4/2/2026 Approved SCOTT FINNILA
Drywall Nailing 4/2/2026 Corrections Issued SCOTT FINNILA
Green Building Rough 4/2/2026 Approved SCOTT FINNILA
HVAC-Rough 4/2/2026 Partial Approval SCOTT FINNILA
METHANE-Rough 4/2/2026 Approved SCOTT FINNILA
PLUMBING-Rough 4/2/2026 Approved SCOTT FINNILA
Verify Sprinkler Sign Off 4/2/2026 Approved SCOTT FINNILA
ELECTRICAL-Final 7/2/2026 Not Ready for Inspection ROY SPAULDING
Final 7/2/2026 Corrections Issued ROY SPAULDING
Green Building Final 7/2/2026 Not Ready for Inspection ROY SPAULDING
HVAC-Final 7/2/2026 Not Ready for Inspection ROY SPAULDING
PLUMBING-Final 7/2/2026 Not Ready for Inspection ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 7/2/2026 SGSOV Not Ready ROY SPAULDING
Smoke Detectors 7/2/2026 Not Ready for Inspection ROY SPAULDING
ELECTRICAL-Final 7/6/2026 Corrections Issued CRAIG VAUGHAN
HVAC-Final 7/6/2026 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 7/6/2026 Approved CRAIG VAUGHAN
Service/Power Release 7/6/2026 Approved CRAIG VAUGHAN
ELECTRICAL-Final 7/9/2026 Approved CRAIG VAUGHAN
Final 7/9/2026 OK to Issue CofO CRAIG VAUGHAN
Green Building Final 7/9/2026 Approved CRAIG VAUGHAN
HVAC-Final 7/9/2026 Approved CRAIG VAUGHAN
PLUMBING-Final 7/9/2026 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 7/9/2026 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 7/9/2026 Approved CRAIG VAUGHAN