4550 W MONROE ST 90029

Certificate Information: 4550 W MONROE ST 90029

Application / Permit
24016-10000-26003
Plan Check / Job No.
B24LA18084
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing garage to new accessory dwelling unit (ADU) per GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g).
Permit Issued
Issued on 9/28/2024
Issuing Office
Current Status
Issued on 9/28/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/14/2024 APPLICANT
Assigned to Plan Check Engineer 8/16/2024 PINANK PATEL
Corrections Issued 8/17/2024 PINANK PATEL
Applicant returned to address corrections 8/28/2024 SARKIS HARABEDIAN
Applicant returned to address corrections 9/6/2024 SARKIS HARABEDIAN
Plan Check Approved 9/25/2024 SARKIS HARABEDIAN
Issued 9/28/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/21/2024 WALLIE JONG
Sewer availability Cleared 8/21/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 9/19/2024 WALLIE JONG
Specific Plan Cleared 9/19/2024 NASHYA JENSEN
ZI Cleared 9/19/2024 NASHYA JENSEN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/3/2024 Approved FREDDIE RIVERA
Pre-Inspection 12/17/2024 Partial Inspection FREDDIE RIVERA
Footing/Foundation/Slab 1/23/2025 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 1/31/2025 Corrections Issued FREDDIE RIVERA
Deputy Drilled-In Anchors 3/19/2025 Conditional Approval FREDDIE RIVERA
Footing/Foundation/Slab 3/20/2025 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 4/8/2025 Corrections Issued JOSE MACIAS
ELECTRICAL-Rough 7/1/2025 Not Ready for Inspection ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 7/1/2025 Approved ARTHUR NEGRETE
PLUMBING-Rough 7/1/2025 Not Ready for Inspection ARTHUR NEGRETE
ELECTRICAL-Rough 9/19/2025 Partial Inspection FREDDIE RIVERA
HVAC-Rough 9/19/2025 Approved FREDDIE RIVERA
PLUMBING-Rough 9/19/2025 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 10/3/2025 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 10/3/2025 Approved FREDDIE RIVERA
PLUMBING-Rough 10/3/2025 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 10/24/2025 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 10/24/2025 Approved FREDDIE RIVERA
Insulation 11/7/2025 Not Ready for Inspection DEVON JACKSON
Interior/Exterior Lathing 11/7/2025 Not Ready for Inspection DEVON JACKSON
Insulation 11/12/2025 Corrections Issued ANTHONY RAMOS
Interior/Exterior Lathing 11/12/2025 Partial Approval ANTHONY RAMOS
Drywall Nailing 1/2/2026 Approved JUSTIN HAWLEY
Shower Pan 1/2/2026 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 1/20/2026 Approved ALEX COLIN
ELECTRICAL-Final 3/16/2026 Corrections Issued FREDDIE RIVERA
Gas Test 4/23/2026 Approved FREDDIE RIVERA
ELECTRICAL-Final 5/18/2026 Corrections Issued FREDDIE RIVERA
Service/Power Release 5/18/2026 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Final 6/1/2026 Not Ready for Inspection FREDDIE RIVERA
Service/Power Release 6/1/2026 Not Ready for Inspection FREDDIE RIVERA