629 N ORANGE DR 90036
Certificate Information: 629 N ORANGE DR 90036
- Application / Permit
- 24016-10000-25764
- Plan Check / Job No.
- B24LA17738
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: SOFT STORY SEISMIC REINFORCEMENT AT BUILDING PARKING GARAGE USING (2) SPECIAL CANTILEVERED COLUMNSW/ GRADE BEAMS.
- Permit Issued
- Issued on 1/13/2025
- Issuing Office
- Current Status
- CofC Issued on 5/21/2026
Permit Application Status History
| Submitted | 8/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2024 | VARAND SARKISIAN |
| Corrections Issued | 8/19/2024 | VARAND SARKISIAN |
| Quality Review Completed | 8/28/2024 | HANS SANTIAGO |
| Plan Check Approved | 12/5/2024 | VARAND SARKISIAN |
| Issued | 1/13/2025 | APPLICANT |
| OK for CofC | 8/26/2025 | DARRYL ARNOLD |
| CofC Issued | 5/21/2026 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 1/13/2025 | KORNEL LELEA |
Contact Information
| Contractor | Sturdy Builds Inc; Lic. No.: 1006879-B | 21300 VICTORY BLVD SUITE 635 WOODLAND HILLS, CA 91367 |
| Engineer | Ding,, Wenzhuo; Lic. No.: C82891 | 5205 SUNNY POINT PL RANCHO PALOS VERDES, CA 90275 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/23/2025 | Corrections Issued | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 1/30/2025 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 2/14/2025 | Corrections Issued | DARRYL ARNOLD |
| Structural Steel Frame | 2/14/2025 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 2/14/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| Interior/Exterior Lathing | 2/21/2025 | Corrections Issued | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 5/9/2025 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 5/9/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 8/20/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 8/20/2025 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 8/20/2025 | Corrections Issued | DARRYL ARNOLD |
| Final | 8/26/2025 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 8/26/2025 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 8/26/2025 | Approved | DARRYL ARNOLD |