4807-4809 S ARLINGTON AVE 90043
Certificate Information: 4807-4809 S ARLINGTON AVE 90043
- Application / Permit
- 24016-10000-25607
- Plan Check / Job No.
- B24LA17545
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT PORTION OF (E) SFD TO A JADU (498 SQ FT) PER 65852.2(E)(1)(A) AND 65852.22. PARTIAL REMODEL TO (E) SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 6/17/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2024 | SUNMIN LEE |
| Corrections Issued | 8/17/2024 | SUNMIN LEE |
| Building Plans Picked Up | 8/20/2024 | APPLICANT |
| Applicant returned to address corrections | 9/17/2024 | ALEXANDER JOO |
| Applicant returned to address corrections | 3/20/2025 | CRISTINA SALAZAR |
| Plan Check Approved | 3/24/2025 | JOSE VELAZQUEZ |
| Issued | 6/17/2025 | APPLICANT |
| CofO in Progress | 6/5/2026 | LUIS CASTRO |
| Permit Finaled | 6/8/2026 | DEROLD HAUFF |
| CofO Issued | 6/8/2026 | DEROLD HAUFF |
| Permit Finaled | 6/8/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/28/2024 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 10/28/2024 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/26/2024 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/18/2025 | Partial Approval | LUIS CASTRO |
| ELECTRICAL-Rough | 8/19/2025 | Corrections Issued | LUIS CASTRO |
| HVAC-Rough | 8/19/2025 | Corrections Issued | LUIS CASTRO |
| PLUMBING-Rough | 8/19/2025 | Corrections Issued | LUIS CASTRO |
| Wood Frame | 8/19/2025 | Conditional Approval | LUIS CASTRO |
| ELECTRICAL-Rough | 9/9/2025 | Partial Approval | LUIS CASTRO |
| HVAC-Rough | 9/9/2025 | Corrections Issued | LUIS CASTRO |
| BUILDING-Rough-Frame | 9/29/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Rough | 9/29/2025 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Rough | 9/29/2025 | Approved | LUIS CASTRO |
| Insulation | 9/29/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 9/29/2025 | Approved | LUIS CASTRO |
| Drywall Nailing | 10/21/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Rough | 10/21/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 11/26/2025 | Partial Approval | ALEX COLIN |
| Final | 2/24/2026 | Corrections Issued | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 2/24/2026 | SGSOV Not Ready | LUIS CASTRO |
| Smoke Detectors | 2/24/2026 | Corrections Issued | LUIS CASTRO |
| Final | 3/13/2026 | Partial Approval | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 3/13/2026 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 3/13/2026 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 5/13/2026 | Approved | LUIS CASTRO |
| Final | 5/13/2026 | OK to Issue CofO | LUIS CASTRO |
| HVAC-Final | 5/13/2026 | Approved | LUIS CASTRO |
| PLUMBING-Final | 5/13/2026 | Approved | LUIS CASTRO |
| Service/Power Release | 6/5/2026 | Approved | LUIS CASTRO |