6727 S 7TH AVE 90043
Certificate Information: 6727 S 7TH AVE 90043
- Application / Permit
- 24016-10000-25318
- Plan Check / Job No.
- B24LA17182
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Exterior/Interior Remodel to (E) Single Family Dwelling . Interior work including reconfigure interior floor plan layout and parititons, and kitchen and bathroom remodel . Exterior work including alter exterior openings including window infill . Work per Wood Frame Prescriptive Provisions .
- Permit Issued
- Issued on 8/16/2024
- Issuing Office
- Current Status
- Permit Finaled on 8/18/2025
Permit Application Status History
| Submitted | 8/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/9/2024 | KELVIN CHUONG |
| Corrections Issued | 8/12/2024 | KELVIN CHUONG |
| Plan Check Approved | 8/14/2024 | GEORGE ALVAREZ |
| Issued | 8/16/2024 | APPLICANT |
| Permit Finaled | 8/15/2025 | WAYNE REGESTER |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 8/20/2024 | Corrections Issued | JOSE MACIAS |
| Pre-Inspection | 8/20/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 10/11/2024 | Corrections Issued | AMIR NAZARIAN |
| HVAC-Rough | 10/11/2024 | Corrections Issued | AMIR NAZARIAN |
| PLUMBING-Rough | 10/11/2024 | Corrections Issued | AMIR NAZARIAN |
| ELECTRICAL-Rough | 10/21/2024 | Corrections Issued | AMIR NAZARIAN |
| HVAC-Rough | 10/21/2024 | Corrections Issued | AMIR NAZARIAN |
| Insulation | 10/21/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| PLUMBING-Rough | 10/21/2024 | Corrections Issued | AMIR NAZARIAN |
| Insulation | 10/25/2024 | Conditional Approval | AMIR NAZARIAN |
| Rough-Elec/Plmb/HVAC | 10/25/2024 | Corrections Issued | AMIR NAZARIAN |
| Shower Pan | 10/25/2024 | Corrections Issued | AMIR NAZARIAN |
| PLUMBING-Rough | 10/29/2024 | Approved | SABAS ALONSO |
| Underground Mechanical | 10/29/2024 | Approved | SABAS ALONSO |
| Drywall Nailing | 11/1/2024 | Approved | AMIR NAZARIAN |
| Shower Pan | 11/1/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Shower Pan | 11/5/2024 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 11/6/2024 | Partial Approval | ALEX COLIN |
| HVAC-Rough | 11/18/2024 | Approved | AMIR NAZARIAN |
| ELECTRICAL-Final | 6/13/2025 | Approved | WAYNE REGESTER |
| Final | 6/13/2025 | Not Ready for Inspection | WAYNE REGESTER |
| HVAC-Final | 6/13/2025 | Conditional Approval | WAYNE REGESTER |
| PLUMBING-Final | 6/13/2025 | Approved | WAYNE REGESTER |
| Smoke Detectors | 6/13/2025 | Corrections Issued | WAYNE REGESTER |
| HVAC-Final | 7/28/2025 | Approved | WAYNE REGESTER |
| Smoke Detectors | 7/28/2025 | Approved | WAYNE REGESTER |
| Final | 8/15/2025 | Permit Finaled | WAYNE REGESTER |