1415 W CALUMET AVE 90026
Certificate Information: 1415 W CALUMET AVE 90026
- Application / Permit
- 24016-10000-25300
- Plan Check / Job No.
- B24LA17152
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. Convert existing garage with unpermitted loft and 1 story addition to new detached ADU. Work per engineer design. per Government Code Section 55.852.2(d)(2).
- Permit Issued
- Issued on 11/20/2024
- Issuing Office
- Current Status
- CofO Issued on 9/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2024 | RACHEL BEYENE |
| Corrections Issued | 9/13/2024 | RACHEL BEYENE |
| Quality Review Completed | 9/25/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 11/1/2024 | RACHEL BEYENE |
| Applicant returned to address corrections | 11/5/2024 | RACHEL BEYENE |
| Plan Check Approved | 11/19/2024 | RAHEL BEYENE |
| Issued | 11/20/2024 | APPLICANT |
| CofO in Progress | 6/5/2025 | FERMIN RUBIO |
| Permit Finaled | 9/16/2025 | DANIEL SANCHEZ |
| Permit Finaled | 9/16/2025 | DANIEL SANCHEZ |
| CofO Issued | 9/16/2025 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/26/2024 | MICHAEL TEMPLE |
| Address approval | Cleared | 10/2/2024 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 10/2/2024 | TREVOR QUAN |
| HPOZ | Cleared | 10/11/2024 | SUKI GERSHENHORN |
| CPC | Cleared | 10/16/2024 | LAMBERT GIESSINGER |
| Hist. Property Cntrct Mgr Appr | Cleared | 10/16/2024 | LAMBERT GIESSINGER |
| Miscellaneous | Cleared | 10/16/2024 | LAMBERT GIESSINGER |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2024 | CHRISTINA BRACO |
| Sewer availability | Cleared | 10/17/2024 | CHRISTINA BRACO |
Contact Information
| Architect | Ragle,, Stephanie Slack; Lic. No.: NA32040 | , |
| Contractor | Tarte Design Build Llc; Lic. No.: 1120612-B | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/25/2024 | Partial Inspection | LUIS CASTRO |
| Deputy Drilled-In Anchors | 12/27/2024 | Conditional Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 12/31/2024 | Partial Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 12/31/2024 | Partial Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 12/31/2024 | Partial Inspection | HAMIK HARTOUNIAN |
| METHANE-Barrier | 12/31/2024 | Partial Inspection | HAMIK HARTOUNIAN |
| METHANE-Rough | 12/31/2024 | Partial Inspection | HAMIK HARTOUNIAN |
| METHANE-Subgrade | 12/31/2024 | Partial Inspection | HAMIK HARTOUNIAN |
| Wood Frame | 12/31/2024 | Partial Inspection | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 1/3/2025 | Partial Approval | FERMIN RUBIO |
| Footing/Foundation/Slab | 1/3/2025 | Partial Approval | FERMIN RUBIO |
| METHANE-Barrier | 1/3/2025 | Approved | FERMIN RUBIO |
| METHANE-Subgrade | 1/3/2025 | Approved | FERMIN RUBIO |
| Green Building Rough | 1/7/2025 | Not Ready for Inspection | FERMIN RUBIO |
| METHANE-Rough | 1/7/2025 | Approved | FERMIN RUBIO |
| Wood Frame | 1/7/2025 | Corrections Issued | FERMIN RUBIO |
| Green Building Rough | 1/14/2025 | Not Ready for Inspection | FERMIN RUBIO |
| Insulation | 1/14/2025 | Not Ready for Inspection | FERMIN RUBIO |
| Wood Frame | 1/14/2025 | Partial Approval | FERMIN RUBIO |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2025 | Approved | FERMIN RUBIO |
| Insulation | 1/16/2025 | Approved | FERMIN RUBIO |
| Drywall Nailing | 1/23/2025 | Partial Approval | JACOB SEGURA |
| Interior/Exterior Lathing | 1/23/2025 | Approved | JACOB SEGURA |
| Final | 2/12/2025 | Corrections Issued | FERMIN RUBIO |
| Footing/Foundation/Slab | 2/12/2025 | Approved | FERMIN RUBIO |
| Green Building Final | 2/12/2025 | Not Ready for Inspection | FERMIN RUBIO |
| Green Building Rough | 2/12/2025 | Approved | FERMIN RUBIO |
| SGSOV-Seismic Gas S/O Valve | 2/12/2025 | SGSOV Not Ready | FERMIN RUBIO |
| Smoke Detectors | 2/12/2025 | Corrections Issued | FERMIN RUBIO |
| Wood Frame | 2/12/2025 | Corrections Issued | FERMIN RUBIO |
| Final | 2/19/2025 | OK to Issue CofO | FERMIN RUBIO |
| Green Building Final | 2/19/2025 | Corrections Issued | FERMIN RUBIO |
| SGSOV-Seismic Gas S/O Valve | 2/19/2025 | SGSOV Approved | FERMIN RUBIO |
| Smoke Detectors | 2/19/2025 | Approved | FERMIN RUBIO |
| Wood Frame | 2/19/2025 | Approved | FERMIN RUBIO |
| Green Building Final | 6/5/2025 | Approved | FERMIN RUBIO |