3991 S HUBERT AVE 90008

Certificate Information: 3991 S HUBERT AVE 90008

Application / Permit
24016-10000-25177
Plan Check / Job No.
B24LA16973
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and interior remodel to (e) 1-story SFD
Permit Issued
Issued on 9/11/2024
Issuing Office
Metro
Current Status
CofO Issued on 5/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/21/2024 APPLICANT
Assigned to Plan Check Engineer 8/21/2024 KELVIN CHUONG
Corrections Issued 8/21/2024 KELVIN CHUONG
Plan Check Approved 9/4/2024 ALEXANDER JOO
Issued 9/11/2024 APPLICANT
CofO in Progress 5/5/2025 LUIS CASTRO
Permit Finaled 5/6/2025 DEROLD HAUFF
CofO Issued 5/6/2025 DEROLD HAUFF
Permit Finaled 5/6/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/22/2024 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 8/23/2024 TREVOR QUAN

Contact Information

Contractor Mcinc Construction Inc; Lic. No.: 1087192-B 12002 PAINTER AVE      WHITTIER, CA 90605

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/11/2024 Conditional Approval ANTHONY EGSON
Footing/Foundation/Slab 10/16/2024 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 10/30/2024 Conditional Approval MICHAEL LEWIS
Underground Mechanical 10/30/2024 Not Ready for Inspection MICHAEL LEWIS
ELECTRICAL-Rough 12/9/2024 Corrections Issued BARRY HACHE
HVAC-Rough 12/9/2024 Not Ready for Inspection BARRY HACHE
PLUMBING-Rough 12/9/2024 Approved BARRY HACHE
ELECTRICAL-Rough 12/13/2024 Corrections Issued BARRY HACHE
HVAC-Rough 12/13/2024 Approved BARRY HACHE
PLUMBING-Rough 12/13/2024 Approved BARRY HACHE
Wood Frame 12/13/2024 Not Ready for Inspection BARRY HACHE
BUILDING-Rough-Frame 12/17/2024 Approved LUIS CASTRO
ELECTRICAL-Rough 12/17/2024 Approved LUIS CASTRO
Green Building Rough 12/17/2024 Approved LUIS CASTRO
Interior/Exterior Lathing 12/17/2024 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 12/20/2024 Conditional Approval NICHOLAS LOPEZ
Insulation 12/20/2024 Approved NICHOLAS LOPEZ
Shower Pan 12/20/2024 Approved NICHOLAS LOPEZ
Drywall Nailing 12/27/2024 Approved LUIS CASTRO
Interior/Exterior Lathing 12/27/2024 Approved LUIS CASTRO
ELECTRICAL-Final 4/7/2025 No Access for Inspection LUIS CASTRO
Final 4/7/2025 No Access for Inspection LUIS CASTRO
Footing/Foundation/Slab 4/7/2025 No Access for Inspection LUIS CASTRO
Gas Test 4/7/2025 No Access for Inspection LUIS CASTRO
Green Building Final 4/7/2025 No Access for Inspection LUIS CASTRO
HVAC-Final 4/7/2025 No Access for Inspection LUIS CASTRO
PLUMBING-Final 4/7/2025 No Access for Inspection LUIS CASTRO
Smoke Detectors 4/7/2025 No Access for Inspection LUIS CASTRO
ELECTRICAL-Final 4/9/2025 Approved LUIS CASTRO
Final 4/9/2025 Corrections Issued LUIS CASTRO
HVAC-Final 4/9/2025 Approved LUIS CASTRO
PLUMBING-Final 4/9/2025 Approved LUIS CASTRO
Final 4/24/2025 Corrections Issued LUIS CASTRO
Footing/Foundation/Slab 4/24/2025 No Access for Inspection LUIS CASTRO
Green Building Final 4/24/2025 No Access for Inspection LUIS CASTRO
Smoke Detectors 4/24/2025 No Access for Inspection LUIS CASTRO
Final 5/2/2025 OK to Issue CofO LUIS CASTRO
Footing/Foundation/Slab 5/2/2025 Approved LUIS CASTRO
Green Building Final 5/2/2025 Approved LUIS CASTRO
Smoke Detectors 5/2/2025 Approved LUIS CASTRO