1919 N ARGYLE AVE 90068

Certificate Information: 1919 N ARGYLE AVE 90068

Application / Permit
24016-10000-25069
Plan Check / Job No.
B24LA16841
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
EPLAN***ALTERATION TO APARTMENT BUILDING TO CONVERT 2 UNITS TO OFFICE AND LUANDRY ROOM REDUCE NUMBER OF UNITS FROM 98 TO 96 UNITS
Permit Issued
Issued on 4/29/2026
Issuing Office
Current Status
CofO Issued on 5/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2024 APPLICANT
Assigned to Plan Check Engineer 8/8/2024 SINA KHOSRAVI
Assigned to Zoning Architect 8/8/2024 FRANCIS AHN
Corrections Issued 8/22/2024 SINA KHOSRAVI
Quality Review Completed 8/29/2024 GARO TELMI
Applicant returned to address corrections 9/16/2024 SINA KHOSRAVI
Applicant returned to address corrections 12/17/2024 SINA KHOSRAVI
Applicant returned to address corrections 2/5/2025 SINA KHOSRAVI
Applicant returned to address corrections 1/2/2026 SINA KHOSRAVI
Applicant returned to address corrections 1/15/2026 SINA KHOSRAVI
Plan Check Approved 2/11/2026 SINA KHOSRAVI
Issued 4/29/2026 APPLICANT
CofO in Progress 5/28/2026 LUIS CCAMACHO
Permit Finaled 5/28/2026 ADAM BURGESS
Permit Finaled 5/28/2026 ADAM BURGESS
CofO Issued 5/28/2026 ADAM BURGESS

Permit Application Clearance Information

Miscellaneous Cleared 2/12/2025 FIPE LEILUA
Fire Marshal Fire Life Safety Cleared 2/28/2025 FIRE DEPARTMENT
Demo/Removal of Rental Units Cleared 10/1/2025 EDWARD JACOBS
Public Housing Cleared 11/5/2025 LUIS ALVAREZ
DAS Clearance Cleared 11/19/2025 SINA KHOSRAVI
Zoning Plan Check Cleared 12/10/2025 FRANCIS AHN

Contact Information

Architect Aldrich,, Thomas Vincent; Lic. No.: C41067 231 N MAIN ST      ORANGE, CA 92868
Contractor Walton Construction Inc; Lic. No.: 1034491-B       ,

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Final 5/1/2026 Partial Inspection LUIS CCAMACHO
Reinforced Concrete Frame 5/1/2026 Not Ready for Inspection LUIS CCAMACHO
Final 5/11/2026 OK to Issue CofO LUIS CCAMACHO
Reinforced Concrete Frame 5/11/2026 Approved LUIS CCAMACHO