6409 W COLGATE AVE 90048

Certificate Information: 6409 W COLGATE AVE 90048

Application / Permit
24016-10000-24928
Plan Check / Job No.
B24LA16615
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND ADDITION TO EXISTING SINGLE FAMILY DWELLING INCLUDING NEW COVERED PORCH, KITCHEN REMODEL, BATHROOMS REMODEL, DOORS AND WINDOWS REPLACEMENT AND REROOF.
Permit Issued
Issued on 8/19/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2024 APPLICANT
Assigned to Plan Check Engineer 8/5/2024 NEHEMIAS RAMOS
Plan Check Approved 8/15/2024 ADAM HEGAZI
Issued 8/19/2024 APPLICANT
CofO Issued 2/1/2025 RICHARD STEINBACH
Permit Finaled 2/1/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/14/2024 JUSTIN BICOL
Roof/Waste drainage to street Cleared 8/14/2024 JUSTIN BICOL

Contact Information

Contractor Projekta Inc; Lic. No.: 1010761-B 2152 DUPONT DR STE 235      IRVINE, CA 92612
Engineer Kim,, Taewon; Lic. No.: C80632 28531 PALOS VERDES DR EAST      RANCHO PALOS VERDES, CA 90275

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 10/15/2024 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 10/15/2024 Partial Approval MEL KHACHATOURIAN
Green Building Rough 10/15/2024 Corrections Issued MEL KHACHATOURIAN
METHANE-Rough 10/15/2024 Approved MEL KHACHATOURIAN
PLUMBING-Rough 10/15/2024 Partial Approval MEL KHACHATOURIAN
HVAC-Rough 10/21/2024 Corrections Issued MEL KHACHATOURIAN
Interior/Exterior Lathing 10/21/2024 Partial Approval MEL KHACHATOURIAN
BUILDING-Rough-Frame 10/24/2024 Approved MEL KHACHATOURIAN
Green Building Rough 10/24/2024 Approved MEL KHACHATOURIAN
HVAC-Rough 10/24/2024 Approved MEL KHACHATOURIAN
PLUMBING-Rough 10/24/2024 Approved MEL KHACHATOURIAN
Insulation 10/30/2024 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 10/30/2024 Approved MEL KHACHATOURIAN
Shower Pan 10/30/2024 Approved MEL KHACHATOURIAN
Drywall Nailing 11/5/2024 Approved SEAN HAUPT
Service/Power Release 12/26/2024 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Final 1/17/2025 Partial Approval MEL KHACHATOURIAN
Final 1/17/2025 Not Ready for Inspection MEL KHACHATOURIAN
Footing/Foundation/Slab 1/17/2025 Approved MEL KHACHATOURIAN
Green Building Final 1/17/2025 Approved MEL KHACHATOURIAN
HVAC-Final 1/17/2025 Approved MEL KHACHATOURIAN
METHANE-Barrier 1/17/2025 Approved MEL KHACHATOURIAN
METHANE-Subgrade 1/17/2025 Approved MEL KHACHATOURIAN
PLUMBING-Final 1/17/2025 Partial Approval MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 1/17/2025 SGSOV Not Ready MEL KHACHATOURIAN
Service/Power Release 1/17/2025 Approved MEL KHACHATOURIAN
Smoke Detectors 1/17/2025 Approved MEL KHACHATOURIAN
Final 1/28/2025 Conditional Approval MEL KHACHATOURIAN
Gas Test 1/28/2025 Approved MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 1/28/2025 SGSOV Approved MEL KHACHATOURIAN