1506 1/2 N BENTON WAY 90026
Certificate Information: 1506 1/2 N BENTON WAY 90026
- Application / Permit
- 24016-10000-24908
- Plan Check / Job No.
- B24LA16583
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) REC. ROOM TO ADU (896.57SQFT) PER STATE LAW NO SQFT ADDED
- Permit Issued
- Issued on 11/12/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2024 | KHUONG TRUONG |
| Corrections Issued | 8/13/2024 | KHUONG TRUONG |
| Quality Review Completed | 8/16/2024 | KEN GILL |
| Building Plans Picked Up | 8/20/2024 | APPLICANT |
| Applicant returned to address corrections | 9/20/2024 | KHUONG TRUONG |
| Plan Check Approved | 11/12/2024 | KHUONG TRUONG |
| Issued | 11/12/2024 | APPLICANT |
| CofO in Progress | 2/13/2025 | HAMIK HARTOUNIAN |
| Permit Finaled | 2/14/2025 | DEROLD HAUFF |
| CofO Issued | 2/14/2025 | DEROLD HAUFF |
| Permit Finaled | 2/14/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/19/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 8/19/2024 | DAVID LOPEZ |
| Hydrant and Access approval | Cleared | 11/7/2024 | GILBERT URREA |
Contact Information
| Architect | , ; Lic. No.: C37076 | , |
| Contractor | Best Bet Builders; Lic. No.: 1110108-B | 780 VALENCIA ST SUITE D LA, CA 90017 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/18/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Pre-Inspection | 11/25/2024 | Partial Inspection | LUIS CASTRO |
| Special/Order Compliance | 12/10/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 1/17/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| Green Building Final | 1/17/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| Green Building Rough | 1/17/2025 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 1/17/2025 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 1/17/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| Wood Frame | 1/17/2025 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 1/22/2025 | Off-Hour Fees Due | |
| Final | 1/28/2025 | Partial Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 1/28/2025 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 1/28/2025 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 1/28/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 2/13/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |