6364 W 80TH ST 90045
Certificate Information: 6364 W 80TH ST 90045
- Application / Permit
- 24016-10000-24784
- Plan Check / Job No.
- B24LA16459
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: 10' - 0" X 15'-8" ADDITION AND A 8'-4" X 26'-0" TRELLIS PATIO ADDITION TO (E) SFD, ENCLOSE 56.73 SF PORTION OF REAR PORCH, ALL WORK PER ENG.
- Permit Issued
- Issued on 10/10/2024
- Issuing Office
- Current Status
- Issued on 10/10/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/9/2024 | KELVIN CHUONG |
| Corrections Issued | 8/12/2024 | KELVIN CHUONG |
| Applicant returned to address corrections | 8/19/2024 | KELVIN CHUONG |
| Applicant returned to address corrections | 8/23/2024 | KELVIN CHUONG |
| Applicant returned to address corrections | 9/5/2024 | MINA HABILI |
| Applicant returned to address corrections | 9/13/2024 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 9/26/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 10/1/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 10/8/2024 | LUISANGEL VALENZUELA |
| Issued | 10/10/2024 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 9/12/2024 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2024 | KIMBERLY HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 9/17/2024 | DARIN LAM |
| Specific Plan | Cleared | 9/24/2024 | JOSHUA JONES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Husain,, Shahzain; Lic. No.: C62744 | 1843 MONTGOMERY RD THOUSAND OAKS, CA 91360 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Final | 6/9/2026 |
| BUILDING-Rough-Frame | 6/9/2026 |
| Smoke Detectors | 6/9/2026 |
| SGSOV-Seismic Gas S/O Valve | 6/9/2026 |
| Green Building Final | 6/9/2026 |
Inspection Request History
| Deputy Drilled-In Anchors | 10/15/2024 | Conditional Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 10/23/2024 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2024 | Partial Approval | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 12/6/2024 | Conditional Approval | MICHAEL ALLEN |
| ELECTRICAL-Rough | 12/6/2024 | Corrections Issued | MICHAEL ALLEN |
| Green Building Rough | 12/6/2024 | Corrections Issued | MICHAEL ALLEN |
| HVAC-Rough | 12/6/2024 | Corrections Issued | MICHAEL ALLEN |
| Interior/Exterior Lathing | 12/6/2024 | Partial Approval | MICHAEL ALLEN |
| PLUMBING-Rough | 12/6/2024 | Approved | MICHAEL ALLEN |
| Shower Pan | 12/6/2024 | Approved | MICHAEL ALLEN |
| Deputy Steel/Welding | 12/9/2024 | Conditional Approval | MICHAEL ALLEN |
| Deputy Wood Construction | 12/9/2024 | Conditional Approval | MICHAEL ALLEN |
| ELECTRICAL-Rough | 12/10/2024 | Approved | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2024 | Conditional Approval | MICHAEL ALLEN |
| Green Building Rough | 12/10/2024 | Conditional Approval | MICHAEL ALLEN |
| HVAC-Rough | 12/10/2024 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 12/10/2024 | Approved | MICHAEL ALLEN |
| Insulation | 12/12/2024 | Approved | MICHAEL ALLEN |
| Drywall Nailing | 12/18/2024 | Approved | MICHAEL ALLEN |
| Green Building Rough | 12/18/2024 | Approved | MICHAEL ALLEN |