854 W AVENUE 37 90065
Certificate Information: 854 W AVENUE 37 90065
- Application / Permit
- 24016-10000-24729
- Plan Check / Job No.
- B24LA16378
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: Interior remodel of 3-story single-family dwelling and interior remodel of ALQ below attached garage. Attached via solid roof breezeway.
- Permit Issued
- Issued on 11/15/2024
- Issuing Office
- Current Status
- Permit Finaled on 6/5/2025
Permit Application Status History
| Submitted | 8/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2024 | MARCELA FRANQUEZ |
| Corrections Issued | 8/27/2024 | MARCELA FRANQUEZ |
| Quality Review Completed | 9/4/2024 | TU HUA |
| Applicant returned to address corrections | 9/27/2024 | MARCELA FRANQUEZ |
| Applicant returned to address corrections | 10/16/2024 | MARCELA FRANQUEZ |
| Plan Check Approved | 11/15/2024 | MARCELA FRANQUEZ |
| Issued | 11/15/2024 | APPLICANT |
| Permit Finaled | 6/4/2025 | ALIZAH MAYAGOITIA |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/29/2024 | MICHAEL TEMPLE |
| Specific Plan | Cleared | 9/17/2024 | PABLO ESTRADA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Salahaldin,, Aws; Lic. No.: C95446 | 100 DESERT LOTUS IRVINE, CA 92618 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/18/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 11/21/2024 | No Access for Inspection | ALIZAH MAYAGOITIA |
| Wood Frame | 11/21/2024 | No Access for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 11/22/2024 | Not Ready for Inspection | LUIS CASTRO |
| Footing/Foundation/Slab | 11/22/2024 | Partial Approval | LUIS CASTRO |
| BUILDING-Rough-Frame | 11/27/2024 | Corrections Issued | OSVALDO PARAMO |
| HVAC-Rough | 11/27/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Pre-Inspection | 11/27/2024 | Partial Inspection | OSVALDO PARAMO |
| ELECTRICAL-Rough | 12/4/2024 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Rough | 12/9/2024 | Conditional Approval | OSVALDO PARAMO |
| ELECTRICAL-Rough | 12/12/2024 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 12/12/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 12/13/2024 | Approved | WILLIAM SIERRA |
| Insulation | 12/19/2024 | Not Ready for Inspection | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 12/23/2024 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 12/23/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 12/23/2024 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 1/6/2025 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 1/6/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 3/4/2025 | Approved | ANTHONY RAMOS |
| Shower Pan | 3/4/2025 | Approved | ANTHONY RAMOS |
| ELECTRICAL-Final | 5/28/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 5/28/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 5/28/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 6/4/2025 | Permit Finaled | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 6/4/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 6/4/2025 | Approved | ALIZAH MAYAGOITIA |