1822 W 41ST ST 90062

Certificate Information: 1822 W 41ST ST 90062

Application / Permit
24016-10000-24414
Plan Check / Job No.
B24LA15946
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Convert (E) detached garage with attached storage to an ADU per GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 10/17/2024
Issuing Office
Current Status
CofO Issued on 9/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2024 APPLICANT
Assigned to Plan Check Engineer 8/15/2024 REZA HAGHIGHAT
Corrections Issued 8/15/2024 REZA HAGHIGHAT
Applicant returned to address corrections 9/18/2024 EDWIN ESPIN
Applicant returned to address corrections 10/9/2024 CAROLEAN BASMA
Plan Check Approved 10/16/2024 JOHNPAUL ISIP
Issued 10/17/2024 APPLICANT
CofO in Progress 9/16/2025 SABAS ALONSO
Permit Finaled 9/18/2025 DEROLD HAUFF
CofO Issued 9/18/2025 DEROLD HAUFF
Permit Finaled 9/18/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/10/2024 TREVOR QUAN
Sewer availability Cleared 9/10/2024 TREVOR QUAN
City Hist. Cultural Monument Cleared 9/13/2024 LAMBERT GIESSINGER
Historic monument Cleared 9/13/2024 LAMBERT GIESSINGER
Eng Process Fee Ord 176,300 Cleared 9/20/2024 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 PO BOX 40237      DOWNEY, CA 90239

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/28/2024 Partial Inspection SABAS ALONSO
Footing/Foundation/Slab 11/21/2024 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 12/23/2024 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 1/3/2025 Corrections Issued BARRY HACHE
Deputy Drilled-In Anchors 1/8/2025 Conditional Approval SABAS ALONSO
Footing/Foundation/Slab 1/10/2025 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 3/7/2025 Approved SABAS ALONSO
ELECTRICAL-Rough 3/26/2025 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 3/26/2025 Approved SABAS ALONSO
Sewer 3/26/2025 Approved SABAS ALONSO
HVAC-Rough 4/14/2025 Approved SABAS ALONSO
ELECTRICAL-Rough 4/22/2025 Partial Approval LUIS CASTRO
Underground Mechanical 4/22/2025 Approved LUIS CASTRO
Green Building Rough 4/24/2025 Approved SABAS ALONSO
PLUMBING-Rough 4/24/2025 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 4/28/2025 Approved SABAS ALONSO
ELECTRICAL-Rough 4/28/2025 Approved SABAS ALONSO
PLUMBING-Rough 4/28/2025 Approved SABAS ALONSO
Insulation 5/12/2025 Not Ready for Inspection SABAS ALONSO
Insulation 6/9/2025 Corrections Issued SABAS ALONSO
Insulation 6/11/2025 Approved LUIS CASTRO
Drywall Nailing 6/23/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 8/5/2025 Approved SABAS ALONSO
Shower Pan 8/5/2025 Approved SABAS ALONSO
Underground Mechanical 8/5/2025 Approved SABAS ALONSO
ELECTRICAL-Final 8/13/2025 Corrections Issued SABAS ALONSO
ELECTRICAL-Final 8/25/2025 No Access for Inspection BARRY HACHE
Final 8/25/2025 Corrections Issued BRENDAN MORELLI
PLUMBING-Final 8/25/2025 No Access for Inspection BARRY HACHE
SGSOV-Seismic Gas S/O Valve 8/25/2025 SGSOV Not Ready BARRY HACHE
Final 9/8/2025 Corrections Issued SABAS ALONSO
HVAC-Final 9/8/2025 Approved SABAS ALONSO
Final 9/15/2025 OK to Issue CofO SABAS ALONSO
Green Building Final 9/15/2025 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 9/15/2025 SGSOV Approved SABAS ALONSO
Smoke Detectors 9/15/2025 Approved SABAS ALONSO