2621 3/4 S VINEYARD AVE 90016

Certificate Information: 2621 3/4 S VINEYARD AVE 90016

Application / Permit
24016-10000-24348
Plan Check / Job No.
B24LA15840
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE AND STORAGE INTO A DETACHED ADU PER STATE LAW
Permit Issued
Issued on 1/16/2025
Issuing Office
Metro
Current Status
CofO Issued on 9/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2024 APPLICANT
Assigned to Plan Check Engineer 8/1/2024 MINA HABILI
Corrections Issued 8/4/2024 MINA HABILI
Building Plans Picked Up 8/5/2024 APPLICANT
Applicant returned to address corrections 12/2/2024 MINA HABILI
Applicant returned to address corrections 12/12/2024 ALEXANDER JOO
Applicant returned to address corrections 1/13/2025 SHANGQIN XIE
Plan Check Approved 1/16/2025 CARLOS MONTES
Issued 1/16/2025 APPLICANT
CofO in Progress 9/18/2025 JUSTIN HAWLEY
No Progress 9/21/2025 DEROLD HAUFF
CofO in Progress 9/21/2025 DEROLD HAUFF
Permit Finaled 9/25/2025 DEROLD HAUFF
CofO Issued 9/25/2025 DEROLD HAUFF
Permit Finaled 9/25/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/25/2024 WALLIE JONG
Sewer availability Cleared 9/25/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 9/26/2024 WALLIE JONG
Construction near power lines Cleared 11/25/2024 RIDWAN HARDY
Tenant Habitability Plan Cleared 12/11/2024 HUGO GARRIDO GARZA

Contact Information

Contractor Vision Adu Llc; Lic. No.: 1115842-B 405 S MISSION DR      SAN GABRIEL, CA 91776
Engineer Allwardt,, Daniel; Lic. No.: S4136 2250 DOUGLAS BLVD 200      ROSEVILLE, CA 95661

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/4/2025 Partial Approval JUSTIN HAWLEY
Pre-Inspection 2/4/2025 Approved JUSTIN HAWLEY
Pre-Inspection 2/4/2025 Not Ready for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 2/6/2025 Not Ready for Inspection JUSTIN HAWLEY
Footing/Foundation/Slab 2/6/2025 Not Ready for Inspection JUSTIN HAWLEY
Footing/Foundation/Slab 2/11/2025 Approved WILLIAM SIERRA
PLUMBING-Rough 2/11/2025 Partial Approval WILLIAM SIERRA
ELECTRICAL-Rough 3/7/2025 Not Ready for Inspection RONNIE MINDANAO
HVAC-Rough 3/7/2025 Not Ready for Inspection RONNIE MINDANAO
PLUMBING-Rough 3/7/2025 Not Ready for Inspection RONNIE MINDANAO
Wood Frame 3/7/2025 Not Ready for Inspection RONNIE MINDANAO
ELECTRICAL-Rough 4/10/2025 Not Ready for Inspection OSVALDO PARAMO
Insulation 4/10/2025 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 4/10/2025 Not Ready for Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 4/17/2025 Not Ready for Inspection WILLIAM SIERRA
ELECTRICAL-Rough 4/17/2025 Corrections Issued WILLIAM SIERRA
Green Building Rough 4/17/2025 Corrections Issued WILLIAM SIERRA
HVAC-Rough 4/17/2025 Corrections Issued WILLIAM SIERRA
MERV13>=Rough 4/17/2025 Approved WILLIAM SIERRA
PLUMBING-Rough 4/17/2025 Corrections Issued WILLIAM SIERRA
BUILDING-Rough-Frame 4/25/2025 Not Ready for Inspection ARTHUR NEGRETE
ELECTRICAL-Rough 4/25/2025 Approved ARTHUR NEGRETE
Green Building Rough 4/25/2025 Not Ready for Inspection ARTHUR NEGRETE
PLUMBING-Rough 4/25/2025 Approved ARTHUR NEGRETE
Insulation 5/6/2025 Corrections Issued RONNIE MINDANAO
Deputy Wood Construction 5/8/2025 Conditional Approval JEFFREY MEAD
HVAC-Rough 5/8/2025 Conditional Approval WILLIAM SIERRA
Interior/Exterior Lathing 5/8/2025 Partial Approval WILLIAM SIERRA
BUILDING-Rough-Frame 5/12/2025 Approved WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 5/12/2025 Approved WILLIAM SIERRA
Green Building Rough 5/12/2025 Approved WILLIAM SIERRA
Insulation 5/12/2025 Corrections Issued WILLIAM SIERRA
Insulation 5/23/2025 Corrections Issued RONNIE MINDANAO
Insulation 5/30/2025 Approved RONNIE MINDANAO
Shower Pan 5/30/2025 Approved RONNIE MINDANAO
Drywall Nailing 6/2/2025 Approved JUSTIN HAWLEY
Insulation 6/2/2025 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 6/2/2025 Approved JUSTIN HAWLEY
Shower Pan 6/2/2025 Approved JUSTIN HAWLEY
Sewer 6/5/2025 Corrections Issued ALEX COLIN
Sewer 6/9/2025 Corrections Issued JUSTIN HAWLEY
Sewer 6/10/2025 Approved ALEX COLIN
Final 6/16/2025 Not Ready for Inspection JUSTIN HAWLEY
Green Building Final 6/16/2025 Not Ready for Inspection JUSTIN HAWLEY
MERV13>=Final 6/16/2025 Not Ready for Inspection JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 6/16/2025 SGSOV Not Ready JUSTIN HAWLEY
Smoke Detectors 6/16/2025 Not Ready for Inspection JUSTIN HAWLEY
ELECTRICAL-Rough 7/10/2025 Approved WILLIAM SIERRA
Underground Mechanical 7/10/2025 Approved WILLIAM SIERRA
Final 7/14/2025 Corrections Issued JUSTIN HAWLEY
Green Building Final 7/14/2025 Not Ready for Inspection JUSTIN HAWLEY
MERV13>=Final 7/14/2025 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 7/14/2025 SGSOV Not Ready JUSTIN HAWLEY
Smoke Detectors 7/14/2025 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 7/23/2025 SGSOV Not Ready JUSTIN HAWLEY
Final 7/25/2025 Corrections Issued JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 8/28/2025 SGSOV Not Ready JUSTIN HAWLEY
Final 9/4/2025 Corrections Issued JUSTIN HAWLEY
Green Building Final 9/4/2025 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 9/4/2025 SGSOV Approved JUSTIN HAWLEY
ELECTRICAL-Final 9/18/2025 Approved JUSTIN HAWLEY
Final 9/18/2025 OK to Issue CofO JUSTIN HAWLEY
HVAC-Final 9/18/2025 Approved JUSTIN HAWLEY
PLUMBING-Final 9/18/2025 Approved JUSTIN HAWLEY