4028 W PERLITA AVE 90039
Certificate Information: 4028 W PERLITA AVE 90039
- Application / Permit
- 24016-10000-24275
- Plan Check / Job No.
- B24LA15778
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CH 93. INSTALL 4 SCCS
- Permit Issued
- Issued on 11/18/2024
- Issuing Office
- Current Status
- Issued on 11/18/2024
Permit Application Status History
| Submitted | 7/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2024 | JESSE VIDUYA |
| Corrections Issued | 8/8/2024 | JESSE VIDUYA |
| Quality Review Completed | 8/16/2024 | HANS SANTIAGO |
| Building Plans Picked Up | 8/19/2024 | APPLICANT |
| Applicant returned to address corrections | 9/17/2024 | JESSE VIDUYA |
| Plan Check Approved | 9/23/2024 | JESSE VIDUYA |
| Issued | 11/18/2024 | APPLICANT |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 11/18/2024 | KORNEL LELEA |
Contact Information
| Contractor | Alpha Structural Inc; Lic. No.: 663409-B | 8334 FOOTHILL BLVD SUNLAND, CA 91040 |
| Engineer | Demers,, Joe Alan; Lic. No.: C71535 | 894 SANTA MARIA CIRCLE DUARTE, CA 91010 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/2/2024 | Approved | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 12/5/2024 | Conditional Approval | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 12/5/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Structural Steel Frame | 12/5/2024 | No Access for Inspection | RAMAZANALI ALMASI |
| Excavation/Setback/Form/Re-Bar | 12/6/2024 | Corrections Issued | DARRYL ARNOLD |
| Interior/Exterior Lathing | 12/20/2024 | Partial Approval | LUIS CCAMACHO |
| Final | 2/19/2025 | No Access for Inspection | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 2/19/2025 | SGSOV Not Ready | MARTIN TAVITIAN |
| Smoke Detectors | 2/19/2025 | No Access for Inspection | MARTIN TAVITIAN |
| Final | 2/21/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 2/21/2025 | SGSOV Not Ready | RAMAZANALI ALMASI |
| Smoke Detectors | 2/21/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Final | 4/1/2025 | Corrections Issued | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 4/1/2025 | SGSOV Not Ready | RAFAEL CORTES |
| Smoke Detectors | 4/1/2025 | Approved | RAFAEL CORTES |