8070 S COWAN AVE 90045

Certificate Information: 8070 S COWAN AVE 90045

Application / Permit
24016-10000-24097
Plan Check / Job No.
B24LA15492
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN CONVERT (E) REC ROOM AND PORTION OF (E) STORAGE ROOM TO ADU PER CA Govt. Code 65852.2(e)(1)(A) PER WFPP
Permit Issued
Issued on 1/11/2025
Issuing Office
Current Status
CofO Issued on 11/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2024 APPLICANT
Assigned to Plan Check Engineer 8/2/2024 JOHNPAUL ISIP
Corrections Issued 8/5/2024 JOHNPAUL ISIP
Plan Check Approved 12/27/2024 ALFREDO JARA
Issued 1/11/2025 APPLICANT
CofO in Progress 10/24/2025 RUBEN RIVAS
Permit Finaled 11/6/2025 RICHARD STEINBACH
CofO Issued 11/6/2025 RICHARD STEINBACH
Permit Finaled 11/6/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 8/6/2024 DARIN LAM
Sewer availability Cleared 8/6/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 8/7/2024 DARIN LAM
Construction within easement Cleared 12/4/2024 TINA MIRANDA
Specific Plan Cleared 12/17/2024 HAMID GHAEMMAGHAMI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/27/2025 Approved MICHAEL ALLEN
Gas Test 5/27/2025 Corrections Issued RUBEN RIVAS
Underground Mechanical 5/27/2025 Partial Approval RUBEN RIVAS
BUILDING-Rough-Frame 5/30/2025 Approved RUBEN RIVAS
ELECTRICAL-Rough 5/30/2025 Approved RUBEN RIVAS
HVAC-Rough 5/30/2025 Approved RUBEN RIVAS
PLUMBING-Rough 5/30/2025 Approved RUBEN RIVAS
Insulation 6/5/2025 Approved RUBEN RIVAS
Interior/Exterior Lathing 6/5/2025 Partial Approval RUBEN RIVAS
Shower Pan 6/5/2025 Approved RUBEN RIVAS
Drywall Nailing 6/17/2025 Approved RUBEN RIVAS
Final 9/24/2025 Corrections Issued RUBEN RIVAS
SGSOV-Seismic Gas S/O Valve 9/24/2025 SGSOV Not Ready RUBEN RIVAS
Smoke Detectors 9/24/2025 Approved RUBEN RIVAS
ELECTRICAL-Final 9/26/2025 Approved RUBEN RIVAS
Final 9/26/2025 Corrections Issued RUBEN RIVAS
Final 10/23/2025 OK to Issue CofO RUBEN RIVAS
SGSOV-Seismic Gas S/O Valve 10/23/2025 SGSOV Approved RUBEN RIVAS
Service/Power Release 11/5/2025 Approved DAVID FEILER