8070 S COWAN AVE 90045
Certificate Information: 8070 S COWAN AVE 90045
- Application / Permit
- 24016-10000-24097
- Plan Check / Job No.
- B24LA15492
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN CONVERT (E) REC ROOM AND PORTION OF (E) STORAGE ROOM TO ADU PER CA Govt. Code 65852.2(e)(1)(A) PER WFPP
- Permit Issued
- Issued on 1/11/2025
- Issuing Office
- Current Status
- CofO Issued on 11/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/2/2024 | JOHNPAUL ISIP |
| Corrections Issued | 8/5/2024 | JOHNPAUL ISIP |
| Plan Check Approved | 12/27/2024 | ALFREDO JARA |
| Issued | 1/11/2025 | APPLICANT |
| CofO in Progress | 10/24/2025 | RUBEN RIVAS |
| Permit Finaled | 11/6/2025 | RICHARD STEINBACH |
| CofO Issued | 11/6/2025 | RICHARD STEINBACH |
| Permit Finaled | 11/6/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 8/6/2024 | DARIN LAM |
| Sewer availability | Cleared | 8/6/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/7/2024 | DARIN LAM |
| Construction within easement | Cleared | 12/4/2024 | TINA MIRANDA |
| Specific Plan | Cleared | 12/17/2024 | HAMID GHAEMMAGHAMI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/27/2025 | Approved | MICHAEL ALLEN |
| Gas Test | 5/27/2025 | Corrections Issued | RUBEN RIVAS |
| Underground Mechanical | 5/27/2025 | Partial Approval | RUBEN RIVAS |
| BUILDING-Rough-Frame | 5/30/2025 | Approved | RUBEN RIVAS |
| ELECTRICAL-Rough | 5/30/2025 | Approved | RUBEN RIVAS |
| HVAC-Rough | 5/30/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Rough | 5/30/2025 | Approved | RUBEN RIVAS |
| Insulation | 6/5/2025 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 6/5/2025 | Partial Approval | RUBEN RIVAS |
| Shower Pan | 6/5/2025 | Approved | RUBEN RIVAS |
| Drywall Nailing | 6/17/2025 | Approved | RUBEN RIVAS |
| Final | 9/24/2025 | Corrections Issued | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 9/24/2025 | SGSOV Not Ready | RUBEN RIVAS |
| Smoke Detectors | 9/24/2025 | Approved | RUBEN RIVAS |
| ELECTRICAL-Final | 9/26/2025 | Approved | RUBEN RIVAS |
| Final | 9/26/2025 | Corrections Issued | RUBEN RIVAS |
| Final | 10/23/2025 | OK to Issue CofO | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 10/23/2025 | SGSOV Approved | RUBEN RIVAS |
| Service/Power Release | 11/5/2025 | Approved | DAVID FEILER |