5173 N GLORIA AVE 91436
Certificate Information: 5173 N GLORIA AVE 91436
- Application / Permit
- 24016-10000-23965
- Plan Check / Job No.
- B24LA15317
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan REMODEL TO (E) SFD. WORK TO INCLUDE REMODEL KITCHEN ,2 BATHROOMS , MOVE CLOSETS OR RESIZE IN 3 BEDROOMS , RAISE FAMILY ROOM FLOOR 10" , AND ALL WINDOWS & SLIDING DOORS TO BE REPLACED .
- Permit Issued
- Issued on 9/18/2024
- Issuing Office
- Current Status
- Permit Finaled on 2/5/2026
Permit Application Status History
| Submitted | 7/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/31/2024 | SAMUEL GONZALEZ |
| Corrections Issued | 8/1/2024 | SAMUEL GONZALEZ |
| Plan Check Approved | 8/4/2024 | SAMUEL GONZALEZ |
| Issued | 9/18/2024 | APPLICANT |
| Permit Finaled | 2/4/2026 | JOHN KIDWELL |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Sweven Remodel Inc; Lic. No.: 1052069-B | , |
| Engineer | Forbes,, Dale Loren; Lic. No.: NA30407 | , |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/16/2024 | Approved | KRISTEN CAUSEY |
| ELECTRICAL-Rough | 10/23/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Shower Pan | 10/23/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 11/1/2024 | Partial Approval | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/1/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Sewer | 11/1/2024 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 11/8/2024 | Partial Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 11/8/2024 | Not Ready for Inspection | THOMAS FINNILA |
| MERV13>=Rough | 11/8/2024 | Approved | THOMAS FINNILA |
| Sewer | 11/8/2024 | Partial Approval | THOMAS FINNILA |
| Shower Pan | 11/8/2024 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 11/20/2024 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 11/20/2024 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 11/26/2024 | Approved | THOMAS FINNILA |
| HVAC-Rough | 11/26/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/26/2024 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 12/10/2024 | Approved | THOMAS FINNILA |
| HVAC-Rough | 12/10/2024 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 12/10/2024 | Approved | THOMAS FINNILA |
| Insulation | 12/13/2024 | Approved | THOMAS FINNILA |
| Drywall Nailing | 1/6/2025 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 1/6/2025 | Partial Approval | JOHN COLEMAN |
| BUILDING-Rough-Frame | 10/30/2025 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 10/30/2025 | Not Ready for Inspection | THOMAS FINNILA |
| MERV13>=Final | 10/30/2025 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 12/18/2025 | Corrections Issued | THOMAS FINNILA |
| Final | 12/18/2025 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Final | 12/18/2025 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Final | 12/18/2025 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 12/18/2025 | SGSOV Approved | THOMAS FINNILA |
| Smoke Detectors | 12/18/2025 | Approved | THOMAS FINNILA |
| Final | 2/4/2026 | Permit Finaled | JOHN KIDWELL |