5173 N GLORIA AVE 91436

Certificate Information: 5173 N GLORIA AVE 91436

Application / Permit
24016-10000-23965
Plan Check / Job No.
B24LA15317
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan REMODEL TO (E) SFD. WORK TO INCLUDE REMODEL KITCHEN ,2 BATHROOMS , MOVE CLOSETS OR RESIZE IN 3 BEDROOMS , RAISE FAMILY ROOM FLOOR 10" , AND ALL WINDOWS & SLIDING DOORS TO BE REPLACED .
Permit Issued
Issued on 9/18/2024
Issuing Office
Current Status
Permit Finaled on 2/5/2026

Permit Application Status History

Submitted 7/29/2024 APPLICANT
Assigned to Plan Check Engineer 7/31/2024 SAMUEL GONZALEZ
Corrections Issued 8/1/2024 SAMUEL GONZALEZ
Plan Check Approved 8/4/2024 SAMUEL GONZALEZ
Issued 9/18/2024 APPLICANT
Permit Finaled 2/4/2026 JOHN KIDWELL

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Sweven Remodel Inc; Lic. No.: 1052069-B       ,
Engineer Forbes,, Dale Loren; Lic. No.: NA30407       ,

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/16/2024 Approved KRISTEN CAUSEY
ELECTRICAL-Rough 10/23/2024 Not Ready for Inspection THOMAS FINNILA
Shower Pan 10/23/2024 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 11/1/2024 Partial Approval THOMAS FINNILA
Interior/Exterior Lathing 11/1/2024 Not Ready for Inspection THOMAS FINNILA
Sewer 11/1/2024 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 11/8/2024 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 11/8/2024 Not Ready for Inspection THOMAS FINNILA
MERV13>=Rough 11/8/2024 Approved THOMAS FINNILA
Sewer 11/8/2024 Partial Approval THOMAS FINNILA
Shower Pan 11/8/2024 Approved THOMAS FINNILA
ELECTRICAL-Rough 11/20/2024 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 11/20/2024 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 11/26/2024 Approved THOMAS FINNILA
HVAC-Rough 11/26/2024 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 11/26/2024 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 12/10/2024 Approved THOMAS FINNILA
HVAC-Rough 12/10/2024 Conditional Approval THOMAS FINNILA
PLUMBING-Rough 12/10/2024 Approved THOMAS FINNILA
Insulation 12/13/2024 Approved THOMAS FINNILA
Drywall Nailing 1/6/2025 Approved JOHN COLEMAN
Interior/Exterior Lathing 1/6/2025 Partial Approval JOHN COLEMAN
BUILDING-Rough-Frame 10/30/2025 Approved THOMAS FINNILA
ELECTRICAL-Final 10/30/2025 Not Ready for Inspection THOMAS FINNILA
MERV13>=Final 10/30/2025 Approved THOMAS FINNILA
ELECTRICAL-Final 12/18/2025 Corrections Issued THOMAS FINNILA
Final 12/18/2025 Not Ready for Inspection THOMAS FINNILA
HVAC-Final 12/18/2025 Corrections Issued THOMAS FINNILA
PLUMBING-Final 12/18/2025 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 12/18/2025 SGSOV Approved THOMAS FINNILA
Smoke Detectors 12/18/2025 Approved THOMAS FINNILA
Final 2/4/2026 Permit Finaled JOHN KIDWELL