621 N BROADWAY 90012
Certificate Information: 621 N BROADWAY 90012
- Application / Permit
- 24016-10000-23918
- Plan Check / Job No.
- B24LA15275
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Bank
- Work Description
- Tenant Improvement for Chase Bank. Interior partitions, finishes, furniture, casework & equipment. New walk-up ATMs with new ramp and canopy.
- Permit Issued
- Issued on 1/31/2025
- Issuing Office
- Current Status
- Permit Finaled on 10/20/2025
Permit Application Status History
| Submitted | 7/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2024 | ARSALAN SHABESTARI |
| Assigned to Zoning Architect | 8/1/2024 | NEVRIK NAVASARTIAN |
| Corrections Issued | 8/3/2024 | ARSALAN SHABESTARI |
| Quality Review Completed | 8/13/2024 | YOUNG KIM |
| Applicant returned to address corrections | 11/19/2024 | ARSALAN SHABESTARI |
| Plan Check Approved | 1/20/2025 | ARSALAN SHABESTARI |
| Issued | 1/31/2025 | APPLICANT |
| Permit Finaled | 10/20/2025 | RONALD JIMENEZ |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2024 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 8/21/2024 | JEANIE LAM |
| Miscellaneous | Cleared | 8/23/2024 | CLAUDE GOODING |
| Miscellaneous | Cleared | 8/23/2024 | CLAUDE GOODING |
| Specific Plan | Cleared | 8/23/2024 | CLAUDE GOODING |
| Grading Pre-Inspection | Cleared | 8/29/2024 | MICHAEL TEMPLE |
| DAS Clearance | Cleared | 12/12/2024 | Daniel San Juan |
| Zoning Plan Check | Cleared | 12/17/2024 | NEVRIK NAVASARTIAN |
| Green Code | Cleared | 1/2/2025 | ARSALAN SHABESTARI |
Contact Information
| Contractor | Stitt J M Construction Inc; Lic. No.: 696272-B | , |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/21/2025 | Approved | RONALD JIMENEZ |
| Pre-Inspection | 4/22/2025 | Not Ready for Inspection | LARRY ARNICK |
| Light Gage Steel Frame | 5/8/2025 | Not Ready for Inspection | LARRY ARNICK |
| Light Gage Steel Frame | 5/12/2025 | Corrections Issued | RONALD JIMENEZ |
| Light Gage Steel Frame | 5/13/2025 | Not Ready for Inspection | RONALD JIMENEZ |
| Light Gage Steel Frame | 5/14/2025 | Not Ready for Inspection | RONALD JIMENEZ |
| Excavation/Setback/Form/Re-Bar | 5/15/2025 | Partial Approval | RONALD JIMENEZ |
| Light Gage Steel Frame | 5/15/2025 | Partial Approval | RONALD JIMENEZ |
| Drywall Nailing | 5/16/2025 | Partial Approval | RONALD JIMENEZ |
| Light Gage Steel Frame | 5/20/2025 | Partial Approval | LARRY ARNICK |
| Structural Steel Frame | 5/20/2025 | Partial Approval | LARRY ARNICK |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2025 | Approved | RONALD JIMENEZ |
| Excavation/Setback/Form/Re-Bar | 5/22/2025 | Not Ready for Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 5/22/2025 | Not Ready for Inspection | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 5/29/2025 | Approved | RONALD JIMENEZ |
| Light Gage Steel Frame | 6/12/2025 | Partial Approval | PAUL BAZERKANIAN |
| Light Gage Steel Frame | 6/18/2025 | Corrections Issued | RONALD JIMENEZ |
| Drywall Nailing | 6/23/2025 | Partial Approval | RONALD JIMENEZ |
| Insulation | 6/25/2025 | Partial Approval | RONALD JIMENEZ |
| Light Gage Steel Frame | 6/25/2025 | Corrections Issued | RONALD JIMENEZ |
| Wood Frame | 6/26/2025 | Partial Inspection | JEFFREY FULTON |
| Drywall Nailing | 6/27/2025 | Not Ready for Inspection | RONALD JIMENEZ |
| Drywall Nailing | 7/1/2025 | Approved | RONALD JIMENEZ |
| Drywall Nailing | 7/2/2025 | Approved | RONALD JIMENEZ |
| Structural Steel Frame | 7/22/2025 | Approved | RONALD JIMENEZ |
| Interior/Exterior Lathing | 8/11/2025 | Approved | RONALD JIMENEZ |
| T-Bar Ceiling | 8/11/2025 | Not Ready for Inspection | RONALD JIMENEZ |
| Pre-Inspection | 8/28/2025 | Approved | RONALD JIMENEZ |
| Final | 10/14/2025 | Not Ready for Inspection | RONALD JIMENEZ |
| Green Building Final | 10/14/2025 | Approved | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 10/14/2025 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 10/14/2025 | Not Ready for Inspection | RONALD JIMENEZ |
| Drywall Nailing | 10/15/2025 | Corrections Issued | RONALD JIMENEZ |
| Final | 10/20/2025 | Permit Finaled | RONALD JIMENEZ |
| Smoke Detectors | 10/20/2025 | Approved | RONALD JIMENEZ |