1051 W AVENUE 37 90065
Certificate Information: 1051 W AVENUE 37 90065
- Application / Permit
- 24016-10000-23846
- Plan Check / Job No.
- B24LA15177
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) RAISED DECK ATTACHED TO (E) 2-STORY SFD W/ ATT GARAGE. DECK: 36'-7"x 15'-0", WILL BE SUPPORTED ON BY PILE AND GRADE BEAMS.
- Permit Issued
- Issued on 3/24/2025
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 5/12/2025
Permit Application Status History
| Submitted | 7/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2024 | ADRIANA LOPEZ |
| Corrections Issued | 8/8/2024 | ADRIANA LOPEZ |
| Quality Review Completed | 8/16/2024 | KEN GILL |
| Building Plans Picked Up | 8/20/2024 | APPLICANT |
| Applicant returned to address corrections | 12/24/2024 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 2/20/2025 | ADRIANA LOPEZ |
| Plan Check Approved | 3/24/2025 | ADRIANA LOPEZ |
| Issued | 3/24/2025 | APPLICANT |
| Permit Finaled | 5/9/2025 | ALIZAH MAYAGOITIA |
Permit Application Clearance Information
| ZA Case | Cleared | 11/18/2024 | JASON CHAN |
| Grading Pre-Inspection | Cleared | 12/24/2024 | ADRIANA LOPEZ |
| Specific Plan | Cleared | 1/13/2025 | PABLO ESTRADA |
| Excavation more than 5-ft deep | Cleared | 2/20/2025 | CALOSHA APPROVED |
Contact Information
| Contractor | Alpha Structural Inc; Lic. No.: 663409-A | 8334 FOOTHILL BLVD SUNLAND, CA 91040 |
| Engineer | Aparicio,, Daniel Gonzalo; Lic. No.: C92121 | 19332 AVENIDA DEL SOL WALNUT, CA 91789 |
| Engineer | Rybak,, Richard; Lic. No.: GE2131 | 20312 TAU PLACE CHATSWORTH, CA 91311 |
| Geologist | Carrle,, Conrad Henry; Lic. No.: EG2359 | 23128 WILDWOOD ROAD NEWHALL, CA 91321 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/1/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 4/14/2025 | Approved | ALIZAH MAYAGOITIA |
| Piling/Pier/Caisson | 4/14/2025 | Approved | ALIZAH MAYAGOITIA |
| Deputy Reinf. Concrete | 4/22/2025 | Conditional Approval | ALIZAH MAYAGOITIA |
| Final | 5/9/2025 | Permit Finaled | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 5/9/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 5/9/2025 | Approved | ALIZAH MAYAGOITIA |